               4.     ASSESSMENT MANAGER CONDITIONS

                                              MATERIAL CHANGE OF USE CONDITIONS
               Building
               1.     The plans submitted for a Development Permit for building works are to comply with the
                      approved plans and the following requirements: -
                      1.1     Provide additional architectural elements to the western façade of the dwelling on Lot
                              187
                      1.2     Duplex dwellings are not to exceed 8 metres in height from natural and finished ground
                              level in accordance with Planning Scheme requirements.
               Land Development
               2.     Prior to undertaking any excavation, the person acting on this permit shall contact public
                      utility service providers to ascertain the location of their underground services.
               3.     Prior to commencement of work relating to a Development Permit for Operational Works, the
                      Applicant shall sign a written undertaking to be responsible for the full cost of repairs to road
                      pavement, footpath, kerb and gutter, or other Council property damaged as a result of
                      construction of the proposed development.
                      If any person acting under this permit damages any Council property or facilities (such as
                      underground drainage, water supply and sewerage) , through any cause whatsoever in the
                      course of, directly or indirectly carrying out development, that person shall forthwith notify the
                      Manager - Land Development and shall forthwith rectify that damage at its cost and to the
                      satisfaction of the Manager - Land Development. Alternatively, the Applicant may request
                      the Council to carry out the rectification works.
                      Any damage to a water main shall be rectified by Council. Any damage to a sewer main shall
                      be undertaken by either Council or a Council approved contractor.
                      In all cases, Council reserves the right to carry out rectification works in an emergency and
                      where no reasonable attempt has been made to complete the rectification works as part of
                      the development.
                      All costs incurred by Council in any rectification works shall be repaid to Council prior to the
                      endorsement of the Plan of Survey.
               4.     Car parking shall be provided within the site as shown on plan A001 dated 21.12.99 as
                      submitted by Bennett Architects except as modified herein for at least 12 spaces including a
                      minimum of 12 covered spaces shall be included on site. The car parking area shall be
                      designed to comply with the provisions of AS 2890.1-1993 for user class 1. The minimum
                      head clearance (headroom) at any point shall be 2.2m.
               5.     Easements for access (volumetric where necessary) shall be created over the driveway and
                      garage areas. Easements for services (volumetric where necessary) shall be created to
                      contain stormwater drainage, water and sewerage.
               6.     A new 1.2 metre wide concrete footpath to Council’s design standards shall be constructed
                      across the total frontage of the site.
                      A Development Permit for Operational Works shall be obtained prior to the commencement
                      of any works. Footpath and property alignment levels maybe obtained from the Works
                      Inspector-Development upon request.
                      Prior to works being taken on maintenance, the remainder of the footpath area shall be
                      topsoiled and established with couch or buffalo turf, free of weeds.
               7.     All redundant vehicular crossings to the site shall be removed and replaced by kerb and
                      channel and footpath paving in accordance with Council’s Standard specifications prior to
                      Council endorsement of the Plan of Survey.




                                                                                                          Page 2 of 8
Document Set ID: 25270716
Version: 4, Version Date: 27/10/2026

Used in these records

About this file

File size
170 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 132000.200176.1 (As Published).pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.