Minor Change Existing Approval - 132000.200176.1 (As Published)
RECONFIGURATION OF A LOT CONDITIONS
1. The lot reconfiguration shall generally be in accordance with Lawrence & Partners Consulting
Surveyors plan number 5696-S1 except as modified herein.
2. Pursuant to Section 3.5.21(6) of the Integrated Planning Act 1997, the currency period is four
(4) years from the day this permit takes effect during which time all conditions must have
been complied with, operational works completed, and the Plan of Survey lodged with the
Council for endorsement.
3. In conjunction with the lodgement of the Plan of Survey for Council endorsement, legal
documentation shall be presented to Council and shall be submitted in the correct form with
the fees prescribed in Council's adopted fee schedule.
4. Pursuant to Section 3.7.3(c) of the Integrated Planning Act, all outstanding rates and charges
due and payable to Noosa Council in respect of the lots being reconfigured shall be paid prior
to endorsement of the Plan of Survey.
5. A contribution toward the provision of beach access shall be paid in accordance with
Council’s Planning Scheme Policy PSP 4 on Beach Access Contributions prior the issue of
a Development Permit for Building Works. The amount of the contribution shall be calculated
at the rate current at the date of payment. An estimate only of the contribution rate as of July
94 was $65 per unit.
6. A contribution in accordance with Planning Scheme Policy PSP 24 for Park Requirements
on Subdivision Applications in lieu of dedication of land shall be paid to Council prior to its
endorsement of the Plan of Survey. The amount of the contribution shall be calculated at the
rate current at the date of payment. An estimate only of the contribution rate as of August
2000 was $2,700 per additional lot. Contributions will be used for providing park facilities in
the nearest town.
7. Prior to Council endorsement of the Plan of Survey, a duly executed copy of any required
Grant of Easement shall be submitted to Council for perusal.
Any changes required by Council’s Solicitor shall be attended to prior to endorsing the Plan
of Survey.
Any necessary Titles Office forms requiring the consent of Council is to be submitted prior to
the endorsing of the Plan of Survey.
8. The site shall be connected to Council’s Water Supply and Sewerage reticulation systems in
accordance with the Water and Sewerage design guidelines at no cost to Council.
9. A programme of works is to be submitted with any application for any Development Permit
for Operational Works detailing the construction schedule and proposed environmental
protection measures.
Where the program is changed for any reason whatsoever, a copy of the revised program
shall be submitted to Council’s Works Inspector within seven (7) days.
10. Operational works shall be carried out in a manner that prevents:-
Pollution of a waterway.
Dust/sand nuisance to residents in the vicinity.
Transfer of dirt and debris onto a public road
Excessive noise (less than 1.5 Dba above ambient measured at the lot boundaries).
Excessive traffic delays (less than 5 minute delays).
Diminution of neighbourhood amenity (long term parking of employees vehicles, parking of
construction equipment etc.).
Page 5 of 8
Document Set ID: 25270716
Version: 4, Version Date: 27/10/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - 132000.200176.1 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 170 KB (small file)
- File type
No other editions are linked here.