Revised Stormwater Management Plan

Attached to the e-mail Response to Council information request - MCU16/0066 & OPW16/0133 - email 2 of 3.

Attached to the e-mail Response to SEQ Water Third Party Advice - MCU16/0066 & OPW16/0133.

of 42

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                              STORMWATER MANAGEMENT PLAN
Client: Hass Holdings ATF The Quasar Trust                                Location: Taylor Court, Cooroy

As the results in Table 6 demonstrates, the stormwater quality management strategies proposed
for the proposed Highway Service Station far exceed the target reduction rates required by the
NSC and the State Planning Policy (2014). The pollutant reduction rates exceed those required by
NSC and SPP to ensure the concentration of pollutants discharging from the site are close to the
WQOs for freshwater within the Lake Macdonald catchment as per Table 2. Table 7 below
indicates the daily concentrations of pollutants determined to potentially leave the site identified
through MUSIC modelling.
                                       Table 7 Daily Pollutant loads

                           Pollutant          WQOs                 MUSIC Model
                             TSS                    6                  18
                             (mg/l)
                              TP                 50                    42.1
                             (µg/l)
                              TN                500                    525
                             (µg/l)


5.0 MAINTENANCE PERIOD
5.1 Bioretention Basin

The proposed bioretention basin will require consideration and management during both the
construction and operational phases of the development. In order to establish vegetation and
treatment functions in the bioretention system, the filter media must be protected from pollutants
commonly generated in the construction phases. During the operational phase, regular
maintenance of bioretention system is required to ensure comprehensive vegetation
establishment, a critical component in stormwater pollutant uptake. Below are details on the
general maintenance periods and requirements for the construction and operational periods.

5.1.1 Maintenance During ‘Construction Phase’

Erosion and sediment control devices will be installed at the commencement of all the staged
works to capture and treat runoff during construction works. The sediment control devices should
be cleaned out as required and at the end of the works. During the construction stage, all sediment
control devices are to be inspected weekly, after runoff generating rain events and prior and after
prolonged site shut downs (e.g. holiday periods).

Following construction of the roadways and buildings on site the basin will be constructed to the
final design and filter media layers and plants will be installed. Leaving the completion of the
bioretention basin until after construction is completed will prevent any potential clogging of the
system during the construction period.

5.2 Rainwater Tank and Stormsacks

Maintenance for the proposed rainwater tank and Stormsacks will follow manufacturers guidelines
and recommendations to maintain the products lifespan.




Covey Associates Pty Ltd                        7                                     Project No: 161968
Consulting Engineers                                                                     100415 Rpt Iss B
Log in to download the original file

Revised Stormwater Management Plan.pdf · 4.6 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.