Revised Stormwater Management Plan
Attached to the e-mail Response to Council information request - MCU16/0066 & OPW16/0133 - email 2 of 3.
Attached to the e-mail Response to SEQ Water Third Party Advice - MCU16/0066 & OPW16/0133.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn STORMWATER MANAGEMENT PLAN
Client: Hass Holdings ATF The Quasar Trust Location: Taylor Court, Cooroy
Table 12 - XP-RAFTS Design Discharges (Unmitigated)
Existing Developed
Peak Peak
Critical Critical
Catchment AEP Flow Flow
Duration Duration
(m3/s) (m3/s)
1% 25 min 0.630 15 min 0.724
Outlet 10% 60 min 0.357 25 min 0.518
39% 60 min 0.219 25 min 0.331
The peak flows discharging from the site have increased in the developed case scenario due to the
resulting increase in impervious area. To reduce the flows to meet non-worsening conditions, a
detention tank is proposed to increase detention capacity on site and reduce the offsite flows.
6.6 Stormwater Detention
The pre-developed and post-developed (mitigated) conditions were modelled in XP-RAFTS to
demonstrate that stormwater flows will not be increased with the inclusion of an appropriately
designed storage device. The increases in peak flows have been mitigated on site through the use
of a detention tank. Detention provided by the bioretention basin to treat water quality will also be
utilised on site.
Refer to Site Plans in Appendix B for the proposed detention tank location and details.
6.6.1 Detention Tank
The flows up to 39% AEP will be directed to and will be detained within the proposed bioretention
basin and flow greater than the 39% AEP will be detained within the detention tank located at the
lowest point of the site in the south western corner. A diversion chamber prior to the bioretention
basin inlet will divert all flow above a 39% AEP event to the detention tank. Refer to Stormwater
Management Plan in Appendix B. The bioretention basin has a storage component 1.25 m deep
with a surface area of 115 m2, providing a storage volume of 143.75m3. The proposed detention
tank dimensions are approximately 5 m wide x 10 m long x 2 m high providing a maximum
detention volume of 100 m3. The combined detention volume provided between the bioretention
basin and the detention basin is 243.75 m3 with a minimum available depth of about 2.7 m. The
required detention is 171m3 peaking at a depth of 2.12 m in the 1% AEP event. The tank will slow
release via one (1) 325 mm orifice plate and a weir 1.5 m high and 0.45 m wide discharging into a
chamber and connecting to an existing stormwater network on site. Refer to the Stormwater
Management Plan in Appendix B for detail.
Table 13 summarises stormwater flows, storage volumes and stage height for the required
detention tank.
Table 13 - Post-Development Conditions – XP-RAFTS
Stormwater Flows for proposed detention basin
Basin Peak
Basin Inflow Peak Depth
Basin AEP Outflow Storage
(m3/sec) (m3/sec) (m) (m3)
1% 0.724 0.624 2.12 171
Det_tank 10% 0.518 0.349 1.78 122
39% 0.331 0.211 1.45 73
XP-RAFTS modelling predicts that the proposed detention tank will reduce the post-development
peak stormwater flows for all critical storm events. Refer to Table 14 below for detail.
Covey Associates Pty Ltd 11 Project No: 161968
Consulting Engineers 100415 Rpt Iss B
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.