                        Co-ordination of Operational Works Assessment
                 2.     Additional application fees apply to Operational Work applications where the different
                        aspects of the works are lodged separately. Significant savings in application fees will
                        result if all works are lodged in a single application.
                        Qualified Person
                 3.     For the purpose of preparing a Geotechnical Report, and for certifying geotechnical
                        stability for the development, a qualified person is considered to be a person who:
                        a)      is a Registered Professional Engineer of Queensland (RPEQ); and
                        b)      has a degree in civil engineering or engineering geology; and
                        c)      has a minimum of 5 years experience in the field of geotechnical engineering or
                                engineering geology.
                        Preparation of a Preliminary Construction Management Plan
                 4.     A preliminary Construction Management Plan must be submitted with the Operational
                        Works application and must address the following:
                        a)      appropriate traffic signage in accordance with the Manual of Uniform Traffic
                                Control Devices (MUTCD)
                        b)      provision for safe vehicle and pedestrian access across the frontage of the site
                                both during daily construction and after daily construction has ceased.
                        c)      it is acknowledged that the preliminary Construction Management Plan will be a
                                draft document requiring finalisation upon appointment of the Principal Contractor
                                employed to construct the works and a final document will be required to be
                                submitted at the Pre-Start Meeting for the project.
                        Private Infrastructure
                 5.     All private infrastructure for the development must be designed to meet the planning
                        scheme requirements unless otherwise agreed by the relevant authority.
                        Infrastructure Charges
                 6.     All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
                        Resolution” made pursuant to the planning legislation and regulations current at the time
                        of issue.
                 4.     REPRESENTATIONS ABOUT REFERRAL AGENCY RESPONSE

                 The applicant may make representations to Council about this referral agency response at
                 any time before the application is decided pursuant to section 30 of the Development
                 Assessment Rules.


                 Yours faithfully,


                 Tiani Bird
                 Development Planner


                 Enc:   Approved Plans/Documents




                                                                                                          Page 5 of 5
Document Set ID: 23794310
Version: 0, Version Date: 01/01/1900

Used in these records

About this file

File size
107 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Referral Agency Response - Minor Change - Planning RAP21 0043.01 (As Published).pdf · 107 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.