Original PDF page 10, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn 5.1.1 Piped Flows (< 10 Year ARI)
Minor event flows would be conveyed by underground pipework
through the development site to Serenity Close and down the existing
pathway to discharge to existing informal wetlands.
It is proposed to upgrade existing pipework and headwalls within the
road reserve and pathway in order to cater for the increased catchment
area but maintain existing alignments and discharge point.
Notably the nett effect would be to combine the two (2) existing
stormwater discharge points into one with flows from the additional
catchment area at the eastern end of Serenity Close effectively moved
around 120m westward.
Refer to Engineering Drawings at Appendix A for details.
5.1.2 Major Event Overland Flows (100 Year ARI)
Emergency overflow, for events (>Q10) which cannot be wholly
conveyed by underground pipework would be conveyed overland
through the development site via a landscaped swale.
Simple manning calculations (Appendix E) have been carried out at three
(3) nodes along the proposed route through the development site and
confirm that 100 Year ARI flows may be conveyed safely in respect to
maximum velocity x depth products (maximum 0.4m2/se3c – QUDM
7.0.4.2) and minimum freeboard (minimum 0.3m – QUDM 7.0.3.5).
Calculations have been performed for both gap flows (Q100-Q10) and
Q100 + 100% blockage conditions.
Calculations have applied a Manning roughness coefficient of 0.035
(short-long grass) reflecting proposed landscape outcomes for the area
as depicted on Architectural drawings at Appendix B.
The proposed swale would ‘daylight’ at the western end of the
development site with emergency flows spreading out into sheet flow
onto Serenity Close.
Existing flush kerbing and grated pit at the end of Serenity Close and
the concrete footpath down to the informal wetland would be reformed
as part of the pipe upsizing works and convey overland flows to the
existing informal wetland.
________________________________________________________________________________________
A6769/22/SWMP/RevB – June 2023 Page 8 of 9
SH/PL
Brah101 Pty Ltd t/as ALTA PROJECTS
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.