RFI - Stormwater Management Plan
Plans and drawings: the text below has words only, no drawings.
Very large file (13.7 MB): may take a few minutes to open.
Original PDF page 32, section 1. The text section number identifies this passage in the reader.
RUNOFF CALCULATIONS EXTERNAL UPSTREAM LOT 1 Macquarie Lodge = 5354m2 Impervious area = 3010m2 (56.2%) assume 70% QUDM Pervious area = 2344m2 LOT 2 Petrie Mansions = 4279m2 Impervious area = 2930m2 (68.5%) assume 70% QUDM Pervious area = 1349m2 LOT 3 Elendra = 2985m2 CATCHMENT TO RIP'S - NOT INCLUDED Impervious area = 2575m2 (86.3%) assume 0.9% Pervious area = 410m2 SERENITY CLOSE (includes portion of banksia ave) = 6101m2 Roadway = 3374m2 (55.3%) assume 0.6% Verge/landscape median (includes footpath) = 2727m2 TOTAL AREA TO EX/1 (IMPERVIOUS AREAS FROM LOTS ONLY + ALL ROAD AREA) = 3010 + 2930 + 6101 = 12041m2 Q10 = Q= 1/360 * (1.0) * 226mm/hr * 1.2041Ha = 0.756m3/s Q100 = Q= 1/360 * (1.0) * 332mm/hr * 1.2041Ha = 1.110m3/s VEGETATION AREA CATCHMENT AREA = 0.404Ha 10% - IMPERVIOUS PAVEMENT (C10 = 0.9) 90% - PERVIOUS DENSE-MEDIUM BUSHLAND WITH HIGH SOIL PERMEABILITY (C10 = 0.25) IMPERVIOUS PORTION CALC q10 = 226mm/hr*(0.404*0.1)*(1.0*0.9)*(1/360) = 0.0228m3/s q100 = 332mm/hr*(0.404*0.1)*(1.2*0.9)*(1/360) = 0.037m3/s PERVIOUS PORTION CALC q10 = 226mm/hr*(0.404*0.9)*(1.0*0.25)*(1/360) = 0.057m3/s q100 = 332mm/hr*(0.404*0.9)*(1.2*0.25)*(1/360) = 0.101m3/s TOTAL CALC q10 = 0.08m3/s q100 = 0.138m3/s
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.