Information Request OPW26 0055 [As Published]
Item – Hydraulic Calculations
No hydraulic calculations have been provided as referenced in Lindsay’s Operational Works
Stormwater Plan (22-0416-F22, Rev. E) dated 10 April 2026.
Information Required
2. Provide hydraulic calculations demonstrating the charged line is functional for the entire
roof area.
Item – Level Spreader
Provide comment from a suitably qualified person (RPEQ) addressing and certifying how the
level spreader complies with Section 3.9 of QUDM whereby there is no ultimate nuisance
caused to the downstream neighbour.
3. DUE DATE FOR RESPONSE TO INFORMATION REQUEST
The due date for providing the requested information is 18 August 2026. Email your response
to [email protected]. Please advise Council of your response to this information request
in accordance with section 13 of the Development Assessment Rules.
If you do not provide a response before the due date, it will be taken as if you have decided
not to respond to the information request and Council will continue with the assessment of
your application.
4. OTHER DETAILS
You can follow the progress of this application online at www.noosa.qld.gov.au. The “Online
Services” page can be accessed via "Quick Links" on the left hand side of the screen.
Should you have any further queries in relation to the above, please do not hesitate to contact
me on the number above.
Yours faithfully,
Daniel Epps
Daniel Epps
Senior Development Engineer
Page 2 of 2