Log in to see the plans as drawnNoosa Civic
Stormwater Management Plan
5 Conclusion
A Stormwater Management Plan has been prepared to support the Noosa Civic expansion. The key findings
of the investigation are detailed below.
Regional Flooding
The Regional flood and storm tide mapping indicates that the proposed development will be above
the regional flood events.
Stormwater Quantity
The proposed development is predicted to increase the peak stormwater discharges from the site.
Mitigation measures as shown in Figure 3 include:
- Utilising storage in the car parks to a maximum depth of 300mm. For the purposes of the
development application assessment, the levels were based on the preliminary engineering
levels.
- Reducing the capacity of the culverts under Hofmann Road to 4/1200x300 and raising the invert
level from 3.05mAHD to 3.35mAHD whilst maintaining a 225 RCP at the original invert level for
low flows; and
- Utilizing the fauna passage as a discharge point for events above a 5 year ARI.
Based on the analysis, the mitigation strategy is predicted to reduce the peak flows to existing
conditions therefore causing no adverse flooding external to the site.
Stormwater Quality
It will be necessary to treat runoff from the site to satisfy the water quality objectives defined by the
State Planning Policy (DSDIP, 2013) and Noosa Shire Council. The proposed mitigation measures
were found to satisfy the applicable water quality objectives.
Given the results obtained with respect to stormwater quality and quantity, it is considered that the site can
be developed from a stormwater management perspective without producing unacceptable impacts.
QIC Noosa Civic Pty Ltd Version Final 11 May 2015
J13041R2_Final SWMP.docx Commercial in Confidence Page 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.