Negotiated Decision Notice - Advice Agency - DPI - 010.2006.00001395.001 [As Published] · 132006.1395

of 19

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                             Officer:            Kerri Coyle
                                             Direct Telephone:   (07) 5449 5223
                                             Response Address:   PO Box 141, Tewantin QLD 4565
                                             Email:              [email protected]
                                             Our Reference:      2006/1395
                                             Your Reference:     SO5-0103
16 May 2008

Department of Primary Industries & Fisheries
PO Box 5165
NAMBOUR QLD 4560



Dear Sir/Madam

                            Negotiated Decision Notice
                                 Integrated Planning Act 1997

Your department was an advice agency for the above application and provided advice to Council in a
letter dated 12 December 2006.
Following representations made by the applicant, Council on 15 May 2008 agreed to issue a
Negotiated Decision Notice.
Details of the negotiated decision are as follows:

1     APPLICATION DETAILS

 Application No:             2006/1395
 Street address:             142 Noosa Drive, Noosa Heads
 Real property               Lot 3 SP 126203
 description:
 Planning Scheme:            Superseded Planing Scheme (Schedule to the Planning Scheme &
                             Strategic Plan 1997)

2     DECISION DETAILS
Council on 24 January 2008 decided to issue the following type of approval:-
    Preliminary Approval for Material Change of Use - Application to be assessed against the
      Superseded Planning Scheme - Multiple Dwelling (10 Units)
In relation to representations, Council decided to issue a Development Permit and:
A.    Agree to change Conditions 1, 2, 15, 16, 17, 27, 30, 34 & 66
B.    Agree to delete Conditions 27.4.2, 27.4.3, 27.5, 27.5.1, 27.5.2, 63 & 64
C.    Refuse to delete Condition 27.11 for the following reasons:
      The site is part of a known koala habitat corridor and therefore in replanting it is appropriate to
      incorporate some koala habitat trees.
D.    Issue a Negotiated Decision Notice
Full text of the other 18 pages

Page 2

                                                  -2-




3     RELEVANT PERIOD OF APPROVAL

The relevant period for this Development Permit is specified in Condition 34.
4     ASSESSMENT MANAGER CONDITIONS

Land Use
1.    Development undertaken in accordance with this approval must generally comply with the
      approved plans. The approved plans are titled and numbered Proposed Site Plan – TP-01,
      Site Plan with Contours – TP-02, Typical Duplex Plans – TP-04 & TP-05 and Proposed
      Sections TP-03 (Project No. 2005-02) prepared by Foster Designs Pty Ltd and Architects and
      dated 17/05/2006 and as may be amended by these conditions.
2.    The applicant is required to lodge plans with Council prior to issue of a Development Permit
      for Operational Works demonstrating compliance with the following requirements:-
      2.1.   The development shall not exceed a maximum building height of 2 storeys and 8 metres
             above natural ground surface and finished ground level.
      2.2.   The roof form of the proposed buildings shall incorporate roof pitching, sunhoods and
             eaves. The buildings rooves shall have a minimum pitch of 5 degrees, shall incorporate
             eave overhangs a minimum 600mm wide and shall not include rooftop terrace areas.
      2.3.   Balconies shall not be enclosed, balustrades shall be constructed of open transparent
             materials, a mix of materials shall be included in the external finishes including light
             weight materials, and no colonnades are used.
      2.4.   The following building setbacks shall be provided:-
             2.4.1.      A minimum of 6m from the Noosa Drive road frontage boundary;
             2.4.2.      A minimum of 4 metres to the southwestern side boundary excluding the
                         carport associated with Unit 4 which shall be setback a minimum of 2.5
                         metres;
             2.4.3.      A minimum of 3 metres to northern side boundary;
             2.4.4.      A minimum of 6 metres to the western rear boundary for Unit 2;
                      2.4.4.1. A minimum of 10 metres for Unit 1; and
                      2.4.4.2. A minimum of 8 metres for Unit 3 as indicated on the approved plans.
3.    The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.
4.    The development footprint shall be setback a minimum of 30 metres from the level of Highest
      Astronomical Tides in Weyba Creek.
5.    Any advertising sign or device is to comply with Council's policies on advertising.
6.    All hot water systems installed shall be either solar systems; electric heat pump systems; or
      gas systems (LPG or natural).
7.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
      certificate lodged with Council at completion of work confirming compliance with the maximum
      allowable building height as required by either the conditions of approval or the Planning
      Scheme.
8.    Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like,
      thus remaining as open structures.

                                                                                                2 of 19

Page 3

                                                -3-



9.    The proposed development shall have all kitchen, laundry and bathroom fittings that comply
      with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
      Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
      Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
      System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
      Dishwashers and washing machines are excluded from this requirement.
10.   The development shall contain a maximum of 10 x 3 bedroom units comprised of 7 buildings
      generally in accordance with the approved plans.
11.   The lengths of wall in one plane, irrespective of projections or setbacks, are to be no greater
      than 16m.
12.   External materials of the development shall consist of natural muted colours and tones to
      further assist the built form of the development to integrate with the surrounding environment.
Open Space
13.   The area of land located at the rear of the site and identified as Open Space – Waterway and
      Conservation Protection by the Strategic Plan as shown on approved plan, Proposed Site Plan
      – TP-01, shall be dedicated to the Crown (with Council as Trustee) for environmental
      protection purposes pursuant to the Land Act. This area of land shall be dedicated to the
      Crown prior to the sealing of the survey plan by Council.
14.   Any security lighting associated with proposed Units 1 – 3 shall be orientated away from this
      area of land to be dedicated to the Crown.
Burrowing Skink
15.   Clearing of existing vegetation identified as Primary Habitat by Map 5 – Potential Skink Habitat
      shall only be permitted within a maximum of 3 metres from the building footprint, as indicated
      on the approved plans, of Units 1 – 3. Map 5 – Potential Skink Habitat accompanies the
      Ecological Assessment Report and has been prepared by Biological and Environmental
      Service and dated 19 may 2006.
16.   The existing vegetation to be retained within the primary habitat areas identified in Map 5 –
      Potential Skink Habitat to the rear of units 1 – 3 and adjacent the north western boundary to
      the required park dedication shall be protected during construction and preparation of the site
      for construction with a temporary wire and steel post fence. Map 5 – Potential Skink Habitat
      accompanies the Ecological Assessment Report and has been prepared by Biological and
      Environmental Service and dated 19 may 2006.
Acoustic Requirements
17.   An acoustic buffer shall be provided on site adjacent to Noosa Drive extending the full length
      of the eastern property boundary. This buffer shall comprise a 2 metre high acoustic fence
      along the eastern property boundary and consist of the following requirements:-
      17.1. The acoustic buffer shall be constructed in a koala friendly manner as outlined in Policy
            1 - Nature Conservation (Koala) Conservation Plan 2006 and Management Program
            2006-2016; and
      17.2. The acoustic buffer shall be setback a minimum of 2 metres from the eastern property
            boundary adjacent to Noosa Drive excluding the area of land where the eastern
            property boundary coincides with the approved reciprocal easement located at the
            northern extent of the eastern property boundary. The acoustic barrier at this location
            shall be provided along the boundary of the property and the western boundary of the
            registered easement.




                                                                                                3 of 19

Page 4

                                               -4-



18.   A noise assessment report prepared by an independent acoustic engineer shall be submitted
      to Council after construction of the acoustic buffer to Noosa Drive. The report is to indicate
      whether the buffer achieves the acoustic requirements of this development approval for single
      storey dwelling houses and advise of any other remedial actions that may need to be
      implemented. The developer shall implement all identified remedial actions to the reasonable
      satisfaction of the Manager Land Use.
19.   Screening species shall be provided to the area of land between the acoustic buffer and the
      access driveway to the site where the acoustic buffer is located along the property boundary
      and the boundary of the easement to create a visual buffer between the acoustic buffer and
      Noosa Drive.
20.   The first floor of units 4 – 10 shall be acoustically designed to ensure road noise does not
      exceed 63dB(A)L10(18hours) based on predicted traffic volumes ten years hence. An acoustic
      report prepared by a suitably qualified consultant shall be lodged with an application for
      Building Works identifying suitable noise mitigation measures for these units.              All
      recommended mitigation measures for the subject units shall be installed prior to occupation.
Koala Management
21.   All clearing of native vegetation on-site shall be in accordance with Section 16 of the Nature
      Conservation (Koala) Conservation Plan 2006 requiring that a koala spotter be present on site
      to protect koalas from death or injury and allow for their safe movement away from areas of
      the site subject to clearing. Koala habitat trees include species of Angophora, Corymbia,
      Eucalyptus, Lophostemon and Melaleuca.
22.   All clearing of native vegetation shall be in accordance with Section 15 of the Nature
      Conservation (Koala) Conservation Plan 2006 requiring that clearing be undertaken in a way
      that complies with the sequential clearing conditions as specified in the relevant Section. The
      requirement shall ensure that koalas living in or near the clearing site have enough time to
      move out of the area without human intervention.
23.   No koalas shall be permitted to be captured or translocated from the site. A tree in which a
      koala is present, and any tree overlapping that tree, shall be left until the koala has moved
      from the tree of its own volition.
Fauna
24.   An experienced wildlife spotter shall be on site at all times during the clearing of any
      vegetation to ensure the survival of faunal species utilising the site as habitat.
Landscape Plans
25.   A Development Permit for Operational Works for landscaping shall be obtained prior to the
      commencement of any landscaping works. All detailed landscape plans for the development
      shall comply with the requirements of the landscaping conditions herein. To this extent the
      landscaping plans shall be prepared by a qualified Landscape Architect or qualified
      horticulturist.
26.   Landscaped areas shall be integrated floristically and structurally with the surrounding native
      vegetation. To be consistent with an ecologically sustainable design philosophy, all species
      located in landscape areas within the developed portion of the site shall be consistent with
      Council’s Landscaping Guidelines – Planning Scheme Policy PSP3.
27.   A Landscape Plan shall be prepared for all of the required building setback areas, including
      the buffer area at the frontage of the site adjacent to Noosa Drive. Where other permits for
      Operational Works for roads, drainage or access are required, the landscaping layout shall be
      based on approved drawings for those operational works. The detailed landscaping plans are
      to address:-


      27.1. Street tree planting to allow good shade canopy once fully mature to Noosa Drive;
                                                                                                4 of 19

Page 5

                                           -5-



27.2. Road & service locations;
27.3. The retention of existing native vegetation within the following areas:-
      27.3.1.    The 2 metre buffer adjacent to Noosa Drive and the required side property
                 setbacks of Units 4 - 10 located to the east of the proposed internal driveway
                 and access and measures employed to ensure this vegetation retention;
      27.3.2.    Around the perimeter of the development footprint of Units 4 – 10; and
      27.3.3.    The required building setbacks and the areas identified as Primary Habitat on
                 Map 5 – Potential Skink Habitat (excluding the building envelopes of Units 1 –
                 3 including a maximum of 2 metres beyond the building footprints of these
                 units as indicated on the approved plans). Map 5 – Potential Skink Habitat
                 accompanies the Ecological Assessment Report and has been prepared by
                 Biological and Environmental Service and dated 19 may 2006.
27.4. Landscaping treatments including dense vegetation to the following:-
      27.4.1.    The 2 metre vegetated buffer adjacent to Noosa Drive;
      27.4.2.    Deleted;
      27.4.3.    Deleted
      27.4.4.    East of the acoustic buffer located on boundary of the property and the
                 registered easement for the site.
27.5. Deleted.
      27.5.1.    Deleted.
      27.5.2.    Deleted.
27.6. All the works and items that the Developer shall undertake or provide to establish and
      secure the rear conservation area prior to dedication.
27.7. Tree protection during construction with particular emphasis on the vegetation to be
      retained on the site included but not limited to the following;-
      27.7.1.    The existing native vegetation to be retained within the required building
                 setbacks of Units 1, 2 and 3 and within the area identified as Primary Habitat
                 on Map 5 – Potential Skink Habitat. Map 5 – Potential Skink Habitat
                 accompanies the Ecological Assessment Report and has been prepared by
                 Biological and Environmental Service and dated 19 may 2006;
      27.7.2.    Vegetation being retained around the perimeter of the development footprint
                 of Units 4 – 10;
      27.7.3.    The area of the land to be dedicated to the Crown located at the rear of the
                 site and designated Open Space Conservation and Waterway Protection
                 under the Strategic Plan;
      27.7.4.    The area of land contained within the required 2 metre building setback at the
                 frontage of the site adjacent to Noosa Drive.
27.8. Site preparation;
27.9. Fences to neighbouring properties;
27.10.Stabilisation of the areas under the suspended slabs with a suitable substrate that
      emulates the production of leaf litter to provide habitat for the Burrowing Skink.
27.11.Habitat enhancement for native fauna, specifically the inclusion and replanting of Koala
      Habitat Species;
27.12.Removal of undesirable species and environmental weed removal and control;
                                                                                          5 of 19

Page 6

                                                  -6-



      27.13.Planting schedules;
      27.14.Planting out procedures and horticultural requirements;
      27.15.Mulching and fertilising procedures;
      27.16.Irrigation and watering procedures;
      27.17.Erosion and sediment control;
      27.18.On-going maintenance;
      27.19.Construction materials and details;
      27.20.Environmental safeguards.
      Such landscaping is to be completed in accordance with the approved landscaping plan prior
      to acceptance of the development On Maintenance.
28.   All underground services, drainage, footpaths, bike paths, roads and other site works shall be
      located to minimize adverse impacts on retained vegetation, particularly their root systems.
29.   Existing trees on the site and within road reserves are to be retained, except where required to
      be removed due to building operations or the conduct of the approved use. These landscape
      plans required to be submitted are to denote areas of existing vegetation or existing trees
      proposed or required to be retained.
Vegetation Management
30.   A vegetation survey shall be submitted to the satisfaction of the Manager Land Use identifying
      vegetation to be retained on site. This shall include at a minimum vegetation within the
      required 2 metre acoustic fence to Noosa Drive, vegetation required to be retained for the
      skink habitat as identified by condition 27 and some groupings of healthy trees in amongst the
      development.
Vegetation Removal and Disposal
31.   Vegetation removal, tree felling and lopping shall be undertaken in an environmentally
      sensitive manner to avoid damaging surrounding vegetation, trees and habitat:-
      31.1. All cleared vegetation shall be suitably processed or removed from the site by a method
            approved by Council;
      31.2. Reproductive components of environmental weed species cleared from the site shall not
            be mulched, with the material to be removed from the site and disposed of in a Council
            approved refuse tip;
      31.3. Burning off is not considered an acceptable means of disposal and is not to take place;
      31.4. During construction, the boundaries of areas of retained and protected vegetation within
            the development area shall be clearly marked for the purpose of preventing access into
            these areas thereby protecting the vegetation and habitat values;
      31.5. All mulch produced on site by mulching cleared vegetation and trees shall specifically
            exclude reproductive material (particularly seeds) from environmental weed species (eg.
            Camphor laurel, lantana, asparagus and umbrella trees).
32.   Security in the form of a cash bond or trading bank guarantee to the sum of $30,000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for operational works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
33.   The requirements of this development approval are to be effected, prior to the use of the
      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
      this approval to effect compliance with conditions.
                                                                                                6 of 19

Page 7

                                                  -7-



34.   The Development Permit lapses if the use has not happened by 24 January 2010, unless an
      application to extend the currency is approved by Council.
35.   The developer must obtain all of the other Development Permits referred to in the Decision
      Notice, prior to obtaining a Development Permit for Building Works.
Building Services
36.   The wall of the garage setback 300mm from the southern side boundary is to be maintenance
      free as per Clause A6 of the Queensland Development Code (QDC) Part 12.
37.   The combined height of the retaining walls and boundary fences must not exceed 2.0 metres
      above natural ground.
Land Development
River Flooding
38.   All habitable rooms proposed on site shall be constructed to comply with Council’s Minimum
      Floor Height requirements as defined in Council’s Planning Scheme and on Council’s Scheme
      Maps at the time of issue of the Building Permit. In this regard a Minimum Floor Height of RL
      2.8 (AHD) is required for all habitable rooms. These levels however are subject to change and
      verification shall be made to Council’s Land Development Section prior to obtaining a
      Development Permit for Building Works.
Vehicle Access
39.   The access driveway to serve Lot 3 on SP 126203 shall be constructed over reciprocal access
      easements ASP126203 and BSP126203 generally in accordance with Fig 2.1 by Callaghan
      and Toth dated 13th June 2007 and Plan no. 990605 by Ken Hicks and Associates dated
      12/10/99 except where modified to facilitate the turning of garbage service vehicles.
40.   The access driveway to serve Lot 3 on SP 126203 shall be designed and constructed so as to
      allow a garbage service vehicle defined in “PSP9 Waste Management” as a AUSTROADS:
      design single unit truck/bus (12.5m) to enter and leave the site in a forward direction.
41.   The driveway shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming. Should any driveways be constructed to
      grades that do not comply with AS2890.1-2004 and AS2890.2-1989, Council will require that
      the driveway be removed and reconstructed to levels that do comply.
42.   All vehicles shall enter and leave the site in a forward direction.
Carparking
43.   Carparking shall be provided within as shown on drawing number TP-01 dated 17/05/06 by
      Foster Designs Pty Ltd Architects.
44.   A minimum of 4 uncovered carpark spaces and 20 covered carpark spaces shall be provided
      on site.
45.   The carparking area shall be designed to comply with the provisions of AS 2890.1-2004 for
      user class A1 with allowance for vehicles to enter and leave the site in a forward gear and with
      a minimum head clearance (headroom) at any point of 2.2m.
46.   All carparking shall be kept, maintained and line-marked in a condition fit for use.
Frontage Works
47.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the
      Noosa Drive frontage of the site in accordance with Planning Scheme Policy PSP1
      Landscaping Guidelines. Grass shall be couch and free of weeds.



                                                                                                7 of 19

Page 8

                                                 -8-



Stormwater Drainage
48.   Stormwater drainage shall be constructed generally in accordance with the report entitled
      “Stormwater Quality Management and Assessment Report” June 2007 by Callaghan and Toth.
49.   Final plans of the drainage design shall be prepared by a Registered Professional Civil
      Engineer and submitted to Council prior to obtaining a Development Permit for Operational
      Works.
50.   All stormwater drainage shall be collected on site and discharged so there is no net increase
      in stormwater runoff from the site.
51.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
      (minimum storage 3000 litres per dwelling/unit ) that is installed to ensure water from the tank
      can be used for external uses (such as watering gardens, irrigation, ornamental ponds, water
      features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets
      internal to the dwelling/building.  All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and
      shall be part of the plumbing application in conjunction with the building approval. The
      location and capacity of the tanks shall be clearly shown on the plans submitted for Building
      Works approval.
52.   To ensure that polluted run-off does not enter Council’s stormwater drainage system,
      stormwater run-off from the carparking areas and the driveways shall have the first flush (the
      first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor provided on site prior to
      being permitted to discharge into Council’s drainage system.
      All other clean stormwater, such as roof water, can be collected on site and discharged
      through a single underground drain line directly into the existing drainage system, bypassing
      the grease/oil arrestor.
      To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
      arrestors, which shall be submitted to the Council for approval prior to obtaining a
      Development Permit for Operational Works.
      The approved maintenance plan shall be incorporated in the Community Management
      Scheme for the development and a copy of this shall be provided for Council’s records prior to
      commencement of the approved Use.
      A Development Permit for Building Works shall not be granted until a Development Permit for
      Operational Works has been issued in regard to the drainage scheme.
53.   All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
54.   The site shall be connected to the Noosa Sanctuary Development sewer reticulation system
      and be constructed in accordance with Council’s standards and requirements at no cost to
      Council.
55.   All sewage shall drainage by means of gravity to the sewage pump station located on lot 2
      SP110327 as per the Deed made on 22 December 1999 between Noosa Council, Aqua Blue
      (Noosa) Pty Ltd and the applicant, Johanna Jacoba Thannhauser.
56.   Should the drainage via gravity not be possible a new arrangement will need to be negotiated
      with Noosa Council
57.   The sewer system is to be kept and maintained in a condition suitable for use and shall not
      cause adverse impacts on the environment.




                                                                                                  8 of 19

Page 9

                                               -9-



Town Water Supply
58.   Connection to Council’s water supply shall be generally in accordance with Plan H-SP-02
      drawn by Brian Burnett & Associates dated 2007.02.12 for Aqua Blue Noosa Sanctuary
      Development.
59.   The site shall be connected to Council’s town water supply and be constructed in accordance
      with Council’s standards and requirements at no cost to Council.
60.   Each individual water connection to the water reticulation system shall extend to the property
      boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
61.   All water meters must be located in an easily assessable location to facilitate unhindered
      reading by Council and/or Council’s contracted water meter readers, and not behind fences or
      locked gates.
62.   For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development
      shall be served by:
      62.1. A single Body Corporate water meter to measure the total water consumption (including
            fire hose reels, but excluding fire hydrants and fire sprinkler systems), and
      62.2. Individual water meters to each tenement capable of being separately rated, and
      62.3. A fire service (fully testable single detector check with metered bypass), where
            applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
            reels).
Acid Sulfate Soils
63.   Deleted.
64.   Deleted.
Erosion and Sediment Control
65.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.
Contributions Towards Council Infrastructure
66.   Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
      upgrading various infrastructure at the rates applicable at the time of payment. An estimate
      only of the contribution amounts under the current Council policies and requirements is
      outlined in the table below:
       Contribution Required For:                                                   Amount:
       PSP16 – Sewerage Headworks Contributions                                     $25,204
       PSP17 – Water Supply Headworks Contributions                                 $36,670
       PSP20 – Pathway Trunk Network Contributions                                  $6,685
       TOTAL Contribution Amount =                                                  $68,559
       Please note, that these amounts are all subject to variations in the Consumer Price Index, All
       Groups Brisbane from June 2007 until the date of payment.



                                                                                               9 of 19

Page 10

                                               - 10 -



      All contributions must be paid prior to the issue of a Development Permit for Operational
      Works
General
67.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
68.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
69.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
Environmental Health
70.   The developer must provide waste storage and disposal facilities in accordance with Planning
      Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and Industrial
      Premises”, including an external imperviously paved area correctly sized for all refuse and
      recycling containers and suitably screened from public places and neighbouring properties. A
      bin wash area is required with a cold-water tap, hose and drain outlet connected to sewer, via
      a bucket trap. The drain outlet is to be designed to prevent storm water entry to the sewerage
      system and this can be achieved with a nib wall 50mm high and up to 700mm x 700mm wide
      (max 0.5m²), or alternatively the waste area can be roofed, or any other design approved by
      Council.
71.   A Waste Management Plan (Operational) in accordance with Planning Scheme Policy No. 9
      “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, must be
      submitted for the day-to-day operation of the development and approved by Council’s Health
      Section prior to issue of development permit for operational works.
      It is critical that waste areas are properly planned. A copy of Planning Scheme Policy No. 9
      explaining exactly how to predict waste quantities and design waste areas is available from
      Council and the web. The Plan shall include the following information: -
          The types of waste that will be generated from the activities approved within the
            development.
          Estimated volumes or tonnage of both recyclables and waste generated.
          Methods to be used for dealing with garden waste.
          Initiatives to minimize waste either by waste prevention, reduction, re-use or recycling.
          Description of procedures for getting all waste to the bins; the storage of bins and the
            collection of bins by the contractor.
          A description of the design details of waste storage and recycling areas including size,
            location, elevation and floor plan, methods of bin washing and system to prevent storm
            water getting into sewer via the bin wash.
          A description of types and volume of waste storage containers to be used.
          The waste and recycling storage area shall include the provision of containers for all
            waste and recycling materials including putresable matter, non-recycling waste, paper/
            cardboard, glass, aluminum/steel cans, waste oil, styrofoam boxes, etc, and bin
            washing facilities connected to sewer.
          A detailed description of vehicular access to collect waste. Where collection is off
            street, access must allow vehicles to enter and leave the site in a forward direction.


                                                                                                10 of 19

Page 11

                                                   - 11 -



72.   A Waste Management Plan (construction and demolition) shall be submitted prior to
      demolition, removal or relocation of any building other than a shed.
      A Waste Management Plan (construction and demolition) is also required for construction of
      15 or more dwelling units or for any business use of greater than 500m².
      Waste Management Plans (construction and demolition) are required to be submitted in
      accordance with Planning Scheme Policy 11, Waste Management Plans see table below.
      Waste storage areas are to provide for adequate separation of all reusable, recyclable and
      waste materials. These shall be located so that they are convenient and safe to use. (Refer to
      Noosa Council Waste Management Code).
      The Plan shall contain the following information:
             The site area for the storage and separation of waste is to be shown on the plan
               drawings accompanying the application.
             A waste management table as indicated below is to be completed showing how waste
               material is to be segregated - recycled – reused or disposed.
           MATERIALS ON-SITE                  DESTINATION
                                              Re-use and Recycling                     Disposal
           Expected       waste   Estimated   On-site             Off-site             *specify
           materials              volume      *specify proposed   *specify             contractor    and
                                  (m³)        re-use or on-site   contractor     and   landfill site or
                                              recycling           recycling outlet     other     disposal
                                              methods                                  site
           Excavation
           material
           Green waste
           Bricks
           Concrete
           Timber-please
           specify
           Plasterboard
           Metals -     please
           specify
           Asbestos
           Other -      please
           specify


      Note * If a demolition contractor is undertaking works, then the Waste Management table is to
      be completed by the demolition contractor.


      The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
      effective reuse and recycling of such materials. Additionally Council rewards those who
      segregate waste by significantly reducing disposal fees at the landfill some items are free.
      Higher gate fees are charged for loads of mixed waste.


                                                                                                  11 of 19

Page 12

                                                  - 12 -



73.   Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool
      pumps etc) shall comply with the following requirements:
      The equipment shall be installed and located in a manner that prevents excessive noise in
      accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-
      the-spot fines) may apply for offences.
      A person must not use equipment on any day if it makes or causes noise to be made –
      From 10pm to 7am: More than the lower of either –
            40 dB(A)
            3 dB(A) above the background noise level
            No audible noise for pool pumps apply during these hours.
      From 7am to 7pm: More than the lower of either –
            50 dB(A)
            5 dB(A) above the background noise level
              From 7pm to 10pm: More than 3 dB(A) above the background noise level.
74.   Submission of written certification from a suitably qualified person confirming that the noise
      levels from all mechanical equipment comply with the cause above when measured at either
      the residential boundary or outside the most exposed part of an affected building, whichever is
      the closest to the equipment.
      The assessment and certification is required immediately after installation of the equipment
      and prior to any occupation of the building, and in a format approved by Council. This
      assessment must take into account noise from any other fixed equipment on the property e.g.
      swimming pool pump, heating/cooling equipment, etc that may increase the overall noise level
      emitted.
      Advice: It is highly recommended that the person you engage to certify the installation is
      involved at the plan development stage so they can recommend where this equipment is best
      located. They can also advise about noise enclosures and can make other suggestions to
      avoid noise problems. It is a lot more costly to try and deal with noise problems after
      everything is built.
75.   Noise from building works associated with residential development shall comply with the
      following –
      75.1. Limited to between 7:00am to 6:30pm Monday to Saturday.
      75.2. All reasonable measures are taken to minimise noise emissions.
      75.3. Not permitted on Sunday or public holidays.
5     REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:

 Referral Trigger               Referral Status   Referral Agency     Referral Address

 Site adjoins a declared fish   Advice            Dept of Primary     PO Box 5165
 habitat area                                     Industries &        NAMBOUR QLD 4560
                                                  Fisheries

A copy of any referral agency conditions is attached.



                                                                                              12 of 19

Page 13

                                               - 13 -



6     APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the development
assessment conditions.

7     ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.    The applicant is advised that development contributions and infrastructure charges applicable
      to this development approval have been based on the following Uses Class/ Uses and
      applicable quantities:-

                  Existing Development                           Approved Development
       Existing Use Class                               Approved Use Class
                                Existing Quantity                                Approved Quantity
              / Use                                           / Use
                                                        Multiple housing –      10 x 3 bedroom
       Detached House          NIL (1 x Vacant Lot)
                                                        Type 4 Conventional     units

2.    The applicant is informed that approval of this development application will trigger an
      Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
      Charges Plan for the estimated amount of $18,997 and is subject to variations in the
      Consumer Price Index, All Groups Brisbane from June 2007 until the date of payment. An
      Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
      Planning Act 1997.
3.    The applicant is informed that payment via credit card transaction will not be an acceptable
      method of payment for development contributions conditioned in this permit or for
      infrastructure charge notices issued separately.
4.    The applicant is advised that a Compliance Permit for all plumbing and drainage works within
      the boundaries of the development site shall be obtained from Council’s Plumbing Services
      Section prior to obtaining a Development Permit for Building Works.
5.    Compliance with the Nature Conservation Act 1992 with regard to the clearing of native
      vegetation that provides habitat for rare, endangered or threatened fauna.
6.    Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
      the cost of operational works exceeds $80,000, then a portable long service leave levy is
      required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
      the approved form issued by the Building and Construction Industry (Portable Long Service
      Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
      declaration outlining the cost of the operational works must be submitted to Council with the
      lodgement of any application for operational works over the site.
7.    The development should be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
      other emissions in accordance with the nuisance provisions of the Environmental Protection
      Regulation 1998 or Council’s Local Law No. 12 – Control of Nuisances.
8.    In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
      cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
      where it could reasonably be expected to move into a roadside gutter, storm water drain or a
      watercourse. On the spot fines apply for such offences.
9.    Prior to the commencement of the development, a plumbing assessment must be obtained
      from Noosa Council’s Plumbing Services Section in accordance with the Plumbing & Drainage
      Act 2002 (as applicable).
                                                                                               13 of 19

Page 14

                                                  - 14 -



10.   No assessment has been carried out in regard to exits, the fire services, fire separation, fire
      resistance levels. The building certifier will assess these aspects as part of the building
      application.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES

Not applicable

9     PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable

10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit               Subject of the required Development Permit
 required
 Development Permit for Building          All Building Works
 Works

 Development Permit for Operational       Landscaping, Carparking & Access, Sive Civil Works,
 Works                                    Frontage Works, Stormwater Drainage, Sewer Reticulation
                                          (including new mains, relocations, diversions, pump stations
                                          & rising mains), Water Reticulation & Filling of Site

 Development Permit for Material          Multiple Dwellings (10 Units)
 Change of Use

 Development Permit for                   Creation of the park to be dedicated to the crown (with
 Reconfiguring a Lot                      Council as trustee) prior to issue of development for MCU –
                                          Multiple Dwelling (10 Units)

11    SELF ASSESSABLE CODES

Nil
12    SUBMISSIONS

There were no properly made submissions about the application.

13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable


                                                                                                    14 of 19

Page 15

                                               - 15 -



14     RIGHTS OF APPEAL
You have continuing appeal rights in respect of Council’s decision on your application. Refer Section
4.1.27. of the Integrated Planning Act 1997.

15     OTHER DETAILS
Should you wish to obtain more information about Council’s decision, electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

DECISION NOTICE HISTORY
 Original Decision Notice issued 24 January
   2008.
 Negotiated Decision Notice issued 15 May
   2008 with amendment to Conditions 1, 2, 15,
   16, 17, 27, 30, 34 & 66, deletion of Conditions
   27.4.2, 27.4.3, 27.5, 27.5.1, 27.5.2, 63 & 64
   but refuse to delete Condition 27.11.
Yours faithfully,




Shane Adamson
MANAGER - LAND USE




                                                                                              15 of 19

Page 16

       - 16 -




Referral Agency Conditions – Department
of Primary Industries & Fisheries
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




                                                 16 of 19

Page 17

- 17 -




         17 of 19


[OCR of page images]
-17-

 

stormwater management, water quality and ASS issues. DPI&F recognises the
responsibilities and expertise of these Agencies in these regards.

DPI&F provides third party advice, as part of its delivery of the objectives of the
Fisheries Act 1994. This third party advice aims to minimise ihe impacts of
development on:

* marine plant communities;

declared Fish Habitat Areas;

tidal and freshwater wetland and waterways,

fish movement; and

the lifecycle and food chain of fish.

the community value of local, regional and state fisheries.

Thank you for the opportunity to provide advice on this matter.

Yours sincerely

pe flo

Habitat Manager (South)
Fisheries and Aquaculture Industry Development

17 of 19

Page 18

                                                            - 18 -




                                                 Appeal Rights
                                                INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated                            (5) If an application is processed under section
Planning Act (Chapter 4).                                            6.1.28(2), appeal rights for submitters for the
                                                                     application are available only for the aspects of the
Division 8 - Appeals to court relating to                            development that would have required public
development applications                                             notification under the repealed Act.
Appeals by applicants                                                      (6) If an application involves assessment against a
4.1.27.(1) An applicant for a development application                concurrence agency code, appeal rights for
may appeal to the court against any of the following-                submitters for the application are not available against
(a) the refusal, or the refusal in part, of a development            the part of the approval that represents the
    application;                                                     concurrence agency’s response for the code.
(b) a matter stated in a development approval,                       Appeals by advice agency submitters
    including any condition applying to the                          4.1.29.(1) An advice agency may, within the limits of
    development, and the identification of a code                    its jurisdiction, appeal to the court about the giving of
                          1
    under section 3.1.6;                                             a development approval for a development
(c) the decision to give a preliminary approval when a               application if-
    development permit was applied for;                              (a) the development application involves impact
(d) the length of a currency period;                                       assessment; and
(e) a deemed refusal.                                                (b) the advice agency told the applicant and the
                                                                           assessment manager to treat its response to the
    (2) An appeal under subsection (1)(a) to (d) must                      application as a submission for an appeal.
be started within 20 business days (the “applicant’s
appeal period”) after the day the decision notice or                       (2) The appeal must be started within 20 business
negotiated decision notice is given to the applicant.                days after the day the decision notice or negotiated
                                                                     decision notice is given to the advice agency as a
    (3) An appeal under subsection (1)(e) may be                     submitter.
started at any time after the last day a decision on the
matter should have been made.                                        Appeals for matters arising after approval given
                                                                     (co-respondents)
Appeals by submitters
                                                                     4.1.30.(1) For a development approval given for a
4.1.28.(1) A submitter for a development application                 development application, a person to whom any of the
may appeal to the court about-                                       following notices have been given may appeal to the
(a) the giving of a development approval, including                  court against the decision in the notice-
    any conditions (or lack of conditions) or other                  (a) a notice giving a decision on a request for
    provisions of the approval; or                                         extension of the currency period for an approval;
(b) the length of a currency period for the approval.                (b) a notice giving a decision on a request to make a
    (2) The appeal must be started within 20 business                      minor change to an approval.
days (the “submitters appeal period”) after the day                        (2) The appeal must be started within 20 business
the decision notice or negotiated decision notice is                 days after the day the notice of the decision is given
given to the submitter.                                              to the person.
    (3) If a person withdraws a submission before the                      (3) Subsection (1)(a) does not apply if the
application is decided, the person may not appeal the                approval resulted from a development application
decision.                                                            (superseded planning scheme) that was assessed as
    (4) If an application involves both impact                       if it were an application under a superseded planning
assessment and code assessment, appeal rights for                    scheme.
submitters are available only for the part of the                          (4) Also, a person who has made a request
application involving impact assessment.                             mentioned in subsection (1) may appeal to the court
                                                                     against a deemed refusal of the request.
                                                                           (5) An appeal under subsection (4) may be started
1
   Section 3.1.6 (Preliminary approval may override local            at any time after the last day the decision on the
planning instrument)                                                 matter should have been made.
                                                                                                                  18 of 19

Page 19

                                                       - 19 -

Division 9 - Appeals to court about other matters               (b) a matter stated in a development approval,
Appeals for matters arising after approval given                    including any condition applying to the
(no co-respondents)                                                 development, and the identification of a code
                                                                                         3
                                                                    under section 3.1.6;
4.1.31.(1) A person to whom any of the following
notices have been given may appeal to the court                 (c) the decision to give a preliminary approval when a
against the decision in the notice-                                 development permit was applied for;
(a) a notice giving a decision on a request to change           (d) the length of a period mentioned in section 3.5.21
    or cancel a condition of a development approval.                currency period;
                                   2
(b) a notice under section 6.1.44 giving a decision to          (e) a deemed refusal.
    change or cancel a condition of a development                   (2) An appeal under subsection (1)(a) to (d) must
    approval.                                                   be started within 20 business days (the “applicant’s
    (2) The appeal must be started within 20 business           appeal period”) after the day the decision notice or
        days after the day the notice of the decision is        negotiated decision notice is given to the applicant.
        given to the person.                                        (3) An appeal under subsection (1)(e) may be
    (3) Also, a person who has made a request                   started at any time after the last day a decision on the
        mentioned in subsection (1)(a) may appeal to            matter should have been made.
        the court against a deemed refusal of the               The Registrar for the Building and Development
        request.                                                Tribunal may be contacted at the website
    (4) An appeal under subsection (3) may be started           http://www.localgovernment.qld.gov.au/
        at any time after the last day the decision on
        the matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises or
the erection of a building or other structure permitted
by the planning scheme may appeal to the court
against the decision or the conditions applied.
    (2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.
For Building Works Only
Rights of appeal conferred by Section 4.2.9 of the
Integrated Planning Act 1997 as follows:
Division 3 – Appeals to tribunals relating to
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application
may appeal to the Building and Development Tribunal
against any of the following-
(a) the refusal, or the refusal in part, of a development
    application;

2
  Section 6.1.44 (Conditions may be changed or cancelled        3
by assessment manager or concurrence agency in certain             Section 3.1.6 (Preliminary approval may override local
circumstances)                                                  planning instrument)




                                                                                                                 19 of 19

Used in these records

About this file

File size
154 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - Advice Agency - DPI - 010.2006.00001395.001 [As Published].pdf · 154 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.