27.13.Planting schedules;
27.14.Planting out procedures and horticultural requirements;
27.15.Mulching and fertilising procedures;
27.16.Irrigation and watering procedures;
27.17.Erosion and sediment control;
27.18.On-going maintenance;
27.19.Construction materials and details;
27.20.Environmental safeguards.
Such landscaping is to be completed in accordance with the approved landscaping plan prior
to acceptance of the development On Maintenance.
28. All underground services, drainage, footpaths, bike paths, roads and other site works shall be
located to minimize adverse impacts on retained vegetation, particularly their root systems.
29. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use. These landscape
plans required to be submitted are to denote areas of existing vegetation or existing trees
proposed or required to be retained.
Vegetation Management
30. A vegetation survey shall be submitted to the satisfaction of the Manager Land Use identifying
vegetation to be retained on site. This shall include at a minimum vegetation within the
required 2 metre acoustic fence to Noosa Drive, vegetation required to be retained for the
skink habitat as identified by condition 27 and some groupings of healthy trees in amongst the
development.
Vegetation Removal and Disposal
31. Vegetation removal, tree felling and lopping shall be undertaken in an environmentally
sensitive manner to avoid damaging surrounding vegetation, trees and habitat:-
31.1. All cleared vegetation shall be suitably processed or removed from the site by a method
approved by Council;
31.2. Reproductive components of environmental weed species cleared from the site shall not
be mulched, with the material to be removed from the site and disposed of in a Council
approved refuse tip;
31.3. Burning off is not considered an acceptable means of disposal and is not to take place;
31.4. During construction, the boundaries of areas of retained and protected vegetation within
the development area shall be clearly marked for the purpose of preventing access into
these areas thereby protecting the vegetation and habitat values;
31.5. All mulch produced on site by mulching cleared vegetation and trees shall specifically
exclude reproductive material (particularly seeds) from environmental weed species (eg.
Camphor laurel, lantana, asparagus and umbrella trees).
32. Security in the form of a cash bond or trading bank guarantee to the sum of $30,000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for operational works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
33. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
6 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - Advice Agency - DPI - 010.2006.00001395.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 154 KB (small file)
- File type
No other editions are linked here.