Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
The results of the modelling against the range of design storms for the development under the existing and
proposed development conditions are shown in Table 3.1 Existing and proposed unmitigated site peak discharge
rates.
                              Table 3.1 Existing and proposed unmitigated site peak discharge rates

                                                                        Ross Crescent
                                                                                                      Qchange
                                           A.E.P               Qexisting    Qproposed    Qchange       (%)
                                                               (m³/s)       (m³/s)       (m³/s)
                                             1EY                0.017        0.017        0.000         0%
                                            50%                 0.019        0.021       0.002         11%
                                           0.2 EY               0.028        0.030       0.002          7%
                                            10%                 0.037        0.037          0           0%
                                             5%                 0.042        0.042          0           0%
                                             2%                 0.048        0.049       0.001          2%
                                             1%                 0.054        0.054       0.000          0%



As expected, the site has increased the total peak flows from the site for a number of storm events. The magnitude
of the change is considered acceptable as the increase in flow rate for frequent events is only 2L/s from the existing
site, and an increase of 1L/s for a 1 in 50 year event – a rare frequency rate. This change is considered relatively
insignificant.

In addition, the surrounding land parcels are not subject to flooding risks due to:

     •    Elevation of the land; and
     •    Rapid infiltration of groundwater into the soil.

As the drainage characteristics of the site have not been significantly altered and are unlikely to result in impacts to
downstream properties, no attenuation of peak flows is proposed for the development.




Project number 20220072
File RECOR Preliminary Stormwater Management Report - 20220072.docx, 2022-09-02                                   Page 8 of 14
Revision 1


P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567       E [email protected]    recorconsulting.com
Log in to download the original file

Approved Plans MCU22-0080.pdf · 11.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.