Skip to the record
Search everything, all in one place.

Original source · versioned page text

2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2

of 68

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Total progress to date
Table 1a presents a summary of the delivery against milestones. Table 1b. presents this information in detail. The
project milestones as per the Partnership Agreement are described in Annex 1.

Table 1a: Total Progress to Date

  #     Deliverable                                                                             Progress
 1.1    1 Technical Advisory Group with TOR established                                         Achieved
 1.2    1 Project Manager appointed                                                             Achieved
 1.3    1 Project Implementation Plan completed and endorsed by Noosa Council                   Achieved
        1 Detailed Risk Assessment included
        1 Communications and Media Plan completed
        1 Monitoring, Evaluation and Reporting Plan completed
 1.4    3 community engagement forums facilitated                                               Achieved
        3 media statements released
 1.5    3 six monthly status updates submitted to Noosa Council                                 On Track
        3 annual reports submitted to Noosa Council
 2.1    1 Habitat suitability model developed which incorporates industry, Kabi Kabi and        Achieved
        public interests
 2.2    1 set of ‘all’ relevant state and local permits for oyster reef restoration obtained    Delayed
 2.3    1 set of engagement records provided to Noosa Council of public and stakeholder         Achieved
        consultations, including one-on-one meetings, open forums, media, etc.
 3.1    1 consultation completed                                                                Achieved
        1 volunteering opportunities identified
 3.2    1 volunteering program defined                                                          Achieved
        1 volunteering program implemented
 4.1    1 approval from Noosa Council secured to restore 2 trial restoration sites              Delayed
        2+ sites recovered with at least overall 80 m shore length of reef constructed
 4.2    1 approval from Noosa Council secured to restore an additional 2+ sites                 Delayed
        2+ additional sites recovered with at least an overall additional 600m 2 surface area
 4.3    1 related reef monitoring program established                                           Achieved
        2 six monthly status reports submitted                                                  Delayed
        2 annual monitoring and evaluation report cards produced and published
 5.1    1 workshop facilitated                                                                  Achieved
 5.2    5 peer review reports submitted to Noosa Council during the three-year term of          On Track
        this Agreement, if requested by Noosa Council.
 5.3    3 study tours facilitated during the three-year term of this Agreement, if requested    On Hold
        by Noosa Council.
 5.4    1 Conservation Action Plan developed, as required                                       On Track
        1 set of Community Workshops facilitated, as required.
 5.5    1 new formal networking connections facilitated to assist Noosa Council with            On Track
        ongoing and future marine conservation activities, as requested
 5.6    1+ presentations given at national conference/s over 3 years                            On Track
        1+ presentations given at international conference/s over 3 years
 5.7    1+ New corporate/ government/ philanthropic alliances formed                            Achieved
        1+ New in-kind support/financial funding contributions secured
 5.8    1 Habitat mapping report, habitat suitability model, PhD study or similar output        On Track
        completed and presented to Noosa Council




                                                                                                                     10
Log in to download the original file

2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2(PDF, 8MB).pdf · 8.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.