Table 1b: Total Progress to Date - Detailed
Deliverables Measurable Expected Progress Total progress to date and notes
outcomes Timeframe
(A1.1) A Technical Advisory 1 Technical 30 April Achieved Terms of Reference (ToR) for the
Group (TAG) is established Advisory Group 2020 TAG finalised
to provide project with TOR
oversight. This will include established Inaugural meeting held 13 May
a clear terms of reference 2020.
(ToR) and consist of
representatives from key TAG meetings are held as
stakeholders (NSC, TNC, required and TAG members
Kabi Kabi and at least two engaged on a regular basis out of
other independent session to advice on project
parties). components and to review
project reports.
(A1.2) Appointment of 1 Project 31 January Achieved Craig Bohm appointed by TNC as
dedicated project manager Manager 2020 Marine Coordinator for South
who is a marine biologist appointed East Queensland, based in
with extensive project Noosa. Position commenced 29
management experience, January 2020.
for the term of the
Agreement.
(A1.3) A Project 1 Project 31 Achieved The project implementation plan
Implementation Plan Implementation December was endorsed by Noosa Shire
detailing at a minimum: Plan completed 2019 Council as the ‘Project
A detailed risk assessment and endorsed by Management Plan’ at its
associated with the Noosa Council Ordinary Meeting held 16 July
project. 2020. The Project Management
A communications and 1 Detailed Risk Achieved Plan included a detailed risk
media plan, outlining Assessment assessment, Communications
media protocols, included and Media Plan and Monitoring,
opportunities and the role Evaluation and Reporting (MER)
of TNC and NSC. 1 Plan.
A monitoring, evaluation Communications Achieved
and reporting plan which and Media Plan The MER Plan was then reviewed
identified ecological and completed by an independent consultant
social monitoring and the recommendations
programs, how they will 1 Monitoring, Achieved responded to and adopted by
be reported on and how Evaluation and TNC.
this will fed-back into the Reporting Plan
project. completed
(A1.4) Participation and 3 community 30 June Achieved Noosa Community Engagement
delivery of public engagement 2022 Workshop - 18 participants
education and forums 7/12/20 (see report below)
facilitated
11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.