2021-09-13 GC Agenda - Item 11 - Attachment 1 - Noosa Oyster Project Annual Report 2
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
engagement forums and 9 Public Information Sessions –
media statements 3 media Achieved 28 participants 14/12/20 (see
statements report below)
released
Produced and distributed:
- 2 editions of Noosa Oyster
Chronicle
- Project information sheet
- Project Q&A sheet
- Rock oyster fact sheet
- Project Brief (restoration sites
and designs)
3 media statements:
Promotion of Noosa Public
Information Sessions (27 Nov to
13 Dec 2020 – social media
circulation
Noosa Reef Builder
announcement – 12 May 2021
Shuck Don’t Chuck restaurants
partnerships in Noosa release –
1/6/2021
2 media articles:
Noosa Today – Back from the
Brink – 15/12/20
Sunshine Coast Daily – Back from
the Brink – 15/12/20
Social media reach = 23,666
people
See Table 4 in this report for
further details.
Previous reporting periods:
Project manager and team met
with more than 70 stakeholder
groups to talk with them about
12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.