Response to RM20205358 Bushfire Vegetation Management Conditional Approval and Council pre-lodgement advice 17 July 2021
The following provides responses to the items contained within Council’s RM20205358 Bushfire Vegetation Management Conditional Approval and pre-
lodgement advice dated 17 July 2021.
Requirement Action and update
RM20205358 Bushfire Vegetation Management Conditional Approval
1. Payment of an application fee of $187.00 and a bond of $643 to be Noted. We request that Council issue an invoice for payment identifying
made at our Customer Service Counter located at level 1, 9 Pelican the current applicable fees.
Street, Tewantin. Please note that return of the bond will be subject
to an inspection of the site after completion of works and the
inspection may take up to 10 working days from datecustomer
advises completion of the works.
2. Contractors that are engaged to undertake tree removal are required to TreeFix ABN 39019550176 has been engaged to undertake the works.
be trained to AQF Level 3 in Arboriculture or equivalent recognised and Please refer to the Arboriculture Qualifications attached as Attachment
with relevant experience. 3
3. Contractors must hold Public Liability Insurance in the sum of $20 million. Please refer TreeFix’s Work Cover and Liability Insurance attached as
Attachment 4.
4. A Dial Before You Dig must be obtained; this can be done A survey of the site has been undertaken to identify site services, please
online at https://www.1100.com.au/ and evidence provided refer to Attachment 5.
that the tree works will notinterfere with existing underground
services.
5. Residents who may be affected by the removal of the tree must be Noted. The site does not have any directly adjoining neighbours in the
notified of thework at least three days in advance. area that the works are to be undertaken.
6. All debris associated with the removal must be removed from the site. Noted. To be undertaken and confirmed post works.
7. Traffic and pedestrian access and management is the Noted. Given the location of the clearing external traffic and pedestrian
responsibility of thecontractor/client. management is not required
8. Work must be undertaken and completed within 28 days of receipt of The contractor is scheduled to undertake the works from the 9th to 13th
approval. May 2022.
9. If required, stumps must be ground to specifications. Noted. Will action where required.