1 Environmental Commitment
1.1 Introduction
The objective of this Environmental management plan and procedure (EMP) is to assist us to responsibly
manage the environmental risks associated with our on-site activities.
This includes complying with all relevant environmental legislation, standards, and codes of practice.
The EMP covers the following areas:
• A list of the project's environmental impacts and risk areas
• An operational plan for managing these risks
• A list of personnel accountable for implementing the operational plan
• Emergency procedures and contact details for relevant authorities
Our commitment is to ensuring that the environmental risks associated with this project are minimised, and
where possible eliminated. It is every contractor's responsibility to read and understand the Environmental
management plan and procedure and the Site Construction Waste Management Plan and comply with their
requirements.
1.2 Using this Plan
The EMP document also refers to the following documents, which can be accessed by clicking on the links
below and throughout this plan. Hard copies of these documents, as well as relevant regulations, codes of
practice, and environmental guidelines, are kept in the Environmental Management folder in the Site
Office.
Environmental Guidelines for Major Construction Sites
Site Construction Waste Management Plan
Waste Management Checklist
Contractor Environmental Compliance Checklist
Environmental Incident Report
Corrective & Preventative Action Report
Weekly Environmental Report
H. Troon Pty. Ltd., Creswick Road, Ballarat. Ph: (03) 5339 2208
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Additional information enclosing Plans, Bioretention and Gross Pollutant Trap Maintenance & Monitoring Plan, Environmental Management PlanRelated documentApplication case desk ↗
About this file
- File size
- 4.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.