Additional information enclosing Plans, Bioretention and Gross Pollutant Trap Maintenance & Monitoring Plan, Environmental Management Plan · OPW11/0023
Plans and drawings: the text below has words only, no drawings.
Us] JT ]r TZIl
TGM Group Pty. Ltd.
1315 Sturt Street
Ballarat VIC 3350
TGM
Engineers. Surveyors
Phone:
Facsimile:
03) 5330 8888
03) 5333 3815
Email: mail(aDtgmgroup corn
& Planners Web: tgmgroup.com
SUNSHINE REGIONAL
COUNCIL ATT: MARK LEWIS ATT:
Michael Carr Architect
ATT: Sho Itoh ATT:
Energex
ATT: Dan San Martin ATT:
McKnight Electrical
ATT: Wes McKnight ATT:
ATT ATT
FROM: G.MANSELL / P.NICOL
DOCUMENT REGISTER AND TRANSMITTAL
Project NamePROPOSED BUNNINGS WAREHOUSE Project Number : Sheet Number:
EUMUNDI-NOOSA ROAD, NOOSAVILLE, QLD. 4400-02-CE 1 of I
ENCLOSED ARE COPIES OF DOCUMENTS AS LISTED BELOW DATE OF ISSUE
Discipline : CIVIL Day 19 4 17j17 17 17 17 18 18 04 0404
Month 0102 02 02 03 03 03 03 03'04104 104
Year 11 11 11 11 11 11 11 11 11 11'11111
Issue No.
DOCUMENT REGISTER Drawing No. REVISIONS
General Notes, Drawing Index Standard Drawing Table 01 101.
PROPOSED INTFRNAL DRAINAGE AND PAVEMENTIAYOUT PLAN & PIT SCHEDULE C02 0 1 02102 04
Civil details Sheet C03 02' 03
General Notes & Drawing Index EC1 01 01
Proposed Roundabout Pavement Layout Plan _ EC2 01 01
Gateway Drive Cross Sections EC3 01 01
Eumundi East Cross Sections EC4 01 01
Eumundi West Cross Sections EC5 01 . 011
Kerb Setout Co-ordinates and levels EC6 01 01'
Overall Site Plan & Padmount Trans-former Site Plan E01 02 0202 03 03 03 03 03
Energex Specifications L 02 02 02 02 02 02 0202
Padrnount-Construct g €&3 01 ' 01 ' 01 02 02 02
Padmount Construction & Retaining Wall Details E03 03 03
Proposed carpark Dimensions Plan, Ramp Plan & Turning Templates D01 02
Proposed Roundabout Pavement Layout Plan RW1 01
Proposed Retaining Wall: East Boundary RW2 01
DISTRIBUTED TO NUMBER OF COPIES
SUNSHINE REGIONAL 1 1 1 4 4
Michael Carr Architect 1
Energex -- . . 1 1 1 1. 2.
McKnight Electrical 1 1 1,
SENT BY:
COJRIER 1.1 MAIL P PICKUP
:]'..R :1FS SFNGFR Y YOURMESSENGER E EMFJL E E E M E E E E E M E E M
REASON FOR ISSUE:
CR A."'QRO VAS FOR CONSTRUCTION P PRELIMINARY
7^'P.CER FORINFORMATION A A X X X X X X X A X X A
FORMAT
RXXXX aCAC'C XIXA HC Hard CWr FSFull Scale
LL -
`^ O g I V
S. H.1 S I1 D - OXF P - ADOBE PDF a d < = d Q. Q- = `^ d S
4400-02-CE Transmittal (Ball) 20th November 2008
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Additional information enclosing Plans, Bioretention and Gross Pollutant Trap Maintenance & Monitoring Plan, Environmental Management PlanRelated documentApplication case desk ↗
About this file
- File size
- 4.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.