ri   BIORETENTION BASIN & GROSS POLLUTANT TRAP
     PURPOSES FUNCTION

t    The bioretention basins installed at Bunnings Noosaville provides treatment of stormwater runoff as
     well as improve the landscape amenity. The gross pollutant trap provides for primary treatment of
     stormwater runoff prior to it discharging into the bioretention basin in order to capture sediment and
     other gross pollutants.




     The purpose of this bioretention basin maintenance plan is to detail the operational phase


I    maintenance requirements of the bioretention basins installed at the proposed Bunnings Warehouse
     at the corner of Gateway Drive and Noosa-Eumundi Dve. Routine maintenance of the bioretention
     basins shall be undertaken by Bunnings to ensure to efficient operation of the stormwater quality
     treatment train.


     This maintenance plan should be read in conjunction with the Surface Water Management Plan for
     the site.


     BIORETENTENTION BASIN
     PLANT ESTABLISHMENT

     Establishment of vegetation within the bioretention basin is of critical importance as vegetation helps
     maintain porosity of the filter media in the basin and removal of excess nutrients (considered a
     pollutant at the high levels typical of urban stormwater runoff). The plant establishment period within
     the first two years is the most intensive maintenance period with watering, weeding, and possible
     replanting to be carried out. The following schedule for watering of plants should be followed:


     •           Week 1-2                  3 visits/week

     •           Week 3-6                 2 visits/week

     •           Week 7-12                 1 visit/week


     •           After Week 12            As required during dry periods




     REGULAR MAINTENANCE

     The Water Sensitive Urban Design Technical Design guidelines for South East Queensland describe
     the following typical maintenance requirements:


         •       Routine inspection of the bioretention basin profile to identify any areas of obvious increased
                 sediment deposition, scouring from storm flows, rill erosion of the batters from lateral inflows,

Used in these records

About this file

File size
4.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Additional information enclosing Plans, Bioretention and Gross Pollutant Trap Maintenance & Monitoring Plan, Environmental Management Plan.pdf · 4.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.