Log in to see the plans as drawn 3.4 Mitigated Scenario
When comparing the peak flows in the existing and developed scenario, increases in
the peak discharge occur at Outlets 2 and 3. As a result a detention system will be
required to be implemented in order to demonstrate non-worsening from the site.
All modeling parameters remain consistent between the developed and mitigated
scenarios, with the addition of a detention system within sub-catchments C and D.
Due to site constraints the detention system has been modeled as a
square/rectangular underground detention system. The storage details included
within the model are provided in Table 18.
Table 18: Storage and Outlet Details of Detention System
Sub-Catchment Storage Storage Height Outlet Pipe
Peak 100yr WSL (m)
Location Volume (m3) (m) Diameter (mm)
SUBC 100 1.0 375 0.87
SUBD 100 1.0 250 0.99
A comparison of the peak flows between the existing, developed and mitigated
scenarios are presented below in Table 19. It can be seen that non-worsening of
peak flows are achieved at each outlet to the site.
Table 19: Comparison of Existing, Developed and Mitigated WBNM Outlet Peak Flows
Existing Peak Developed Peak Mitigated Peak
Reduction
Flow (m3/s) Flow (m3/s) Flow (m3/s)
Outlet 1
2 0.73 0.69 0.69 -0.04
10 1.02 0.95 0.95 -0.07
100 1.40 1.31 1.31 -0.09
Outlet 2
2 0.14 0.19 0.14 0.00
10 0.19 0.26 0.19 0.00
100 0.26 0.35 0.25 -0.02
Outlet 3
2 0.07 0.13 0.07 0.00
10 0.10 0.18 0.10 -0.01
100 0.14 0.25 0.13 -0.01
20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.