4 Conclusions

It can be seen from the results, presented in Table 10 and Table 11 that the
treatment train proposed for the development site achieves the performance
criteria set by the Sunshine Coast Regional Council. Annual Load Reductions of Total
Suspended Solids (TSS), Total Phosphorus (TP), Total Nitrogen (TN) and Gross
Pollutants (GP) between the Mitigated and Unmitigated Scenarios have been met.
It is proposed for the site to implement two detention systems within the catchment
in order to achieve Council’s non-worsening criteria. Table 19 provides a
comparison of the peak existing, developed and mitigated flows. It can be seen that
whilst peaks flows increase at Outlets 2 and 3, the modeled mitigation solutions
ensure non-worsening is achieved. Mitigation to Outlet 1 is not required due to a
reduction in overall catchment area in the developed scenario.
This plan demonstrates that effective treatment of stormwater at the proposed
development can be achieved through the integration of Water Sensitive Urban
Design (WSUD) principles. Through the incorporation of swales, GPT’s and
stormwater reuse tanks, the plan successfully demonstrates:
•    Compliance with the requirements of Sunshine Coast Regional Council’s Load
     Based Objectives;
•    Ecological sustainability in terms of the development’s impact upon receiving
     waters and the viability of the proposed site development; and
•    Compliance with SCRC non-worsening of peak flows in the 2, 10 and 100 year
     ARI storm event.




                                                                                       21
Log in to download the original file

Engineering Hydrology Plans (IWMP).pdf · 5.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.