Attachment 7A - Responses to NC Info Request by ADG

of 2

Page text shows just the words. Original shows the document exactly as it was published.

           Noosa Council
           PO Box 141
           TEWANTIN QLD 4565


           Attention: Patrick Murphy – Coordinator Planning

           Your Ref: MCU22/0118
           Our Ref: 22366 C L002
           14th December 2022
           MVI / am
           Sunshine Coast Office

           RE:   94 AND 142 NOOSA DRIVE, NOOSA HEADS QLD 4567, LOT 3 ON SP126203, LOT 0 ON
                 SP203417 & LOT 203 ON SP267424
                 APPLICATION REF: MCU22/0118
                 RESPONSE TO INFORMATION REQUEST


           On behalf of RACV Ltd, ADG Engineers provides the following civil engineering responses to the information
           request issued by Noosa Council on the 29th of August 2022 and 2nd of September 2022, associated with 94
           and 142 Noosa Dr, Noosa Heads (Lot 3 on SP126203, Lot 0 on SP203417 & Lot 203 on SP267424).

            INFORMATION REQUEST ITEM                 ADG RESPONSE

            GENERAL ENGINEERING

            1. The submitted planning refers to      We understand Attachment 8 – Site Based Stormwater
               “Attachment 8 – Site Based            Management Plan had been submitted and responded to with
               Stormwater Management Plan by         NC 2nd Information Request by Noosa Council.
               ADG” but the SWMP was not
               attached.
            FLOOD IMMUNITY REQUIREMENTS
            2. Obtain a flood search certificate     It is noted that the flood hazard overlay for 142 Noosa Drive,
               for the site and demonstrate that     Noosa Heads shows an overlay in the north-western corner of
               the minimum surface and floor         the lot at approx. RL2.4m AHD. Given the car park, walkways
               levels required by Table 8.2.6.4      and building for the proposed site are to be suspended and
               of the Flood Hazard Overlay           located at a minimum RL of 3.4m, there is a minimum of 1.0m
               Code are achieved for the car         between the assumed defined flood event and finished floor
               park, walkways and buildings          level of the suspended Cabins. Refer to architectural plans
               proposed for the site.                included in Appendix B of the SBSMP.

            STORMWATER QUALITY TARGETS

            3. Provide an updated SWMP and           Updated SBSMP and MUSIC modelling provided to illustrate the
               updated MUSIC modelling which         HEV status of the receiving waters and demonstrating that the
               recognises the HEV status of the      development causes negligible or nil increase in gross
               receiving      waters       and       pollutants, total suspended solids, total phosphorous and total
               demonstrates that PO6 and             nitrogen compared to the pre-development scenario.
               AO6.1 of the Water Quality and
               Drainage Code has been
               achieved.


BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH                   ABN 63 131 876 143
Log in to download the original file

Attachment 7A - Responses to NC Info Request by ADG.pdf · 290 KB (small file)

Full text of the other 1 page

Page 2

 STORMWATER TREATMENT DEVICE DETAILS

 4. Clarify the filter media area          Refer updated SBSMP (ADG Ref: 22366 C R10 Rev04) that
    proposed for the bioretention          provides a preliminary section showing integration with car
    device and provide a preliminary       parking and surrounding.
    section showing how it integrates
    with the proposed car parking
    and surrounding levels
 5. Provide geotechnical borehole          Refer geotechnical borehole and test results for neighbouring
    and test results demonstrating         development “Noosa Sanctuary” (Report No.
    that the proposed ‘pipeless’           GEOTKPAR1178AA/A) that is included as an appendice in
    bioretention will function at the      ADG’s SBSMP. The bio-retention basin is likely to sit
    proposed location by providing         approximately 0.7m – 1.0m beneath existing surface level.
    the following for the bioretention     Geotech borehole logs identify a medium dense silty sand
    location:                              (alluvial) at approximately 1.0m depth beneath existing ground
                                           level (varies).
     5.1. In-situ Soil classification
     5.2. Groundwater level (BGL and       The groundwater was noted at depths of 1.3m below ground
          mAHD)                            surface level and as the subsurface profile is predominately
                                           sands, the water table is likely to fluctuate with tides, flood and
                                           rainfall events.

     5.3. In-situ saturated hydraulic      It is recommended that in-situ saturated hydraulic conductivity
          conductivity test results at     testing is performed during detailed design to confirm the
          proposed level of bioretention   modelling assumptions. Assumptions included in the SBSMP
          base                             are that a silty sand will have a minimum hydraulic
                                           conductivity, k, of 1.0 * 10^-8 m/s and a maximum hydraulic
                                           conductivity of 5.0 * 10^-6. An appropriate hydraulic
                                           conductivity has been assumed between these ranges and it is
                                           recommended that a hydraulic conductivity and permeability
                                           test be conducted by an experienced Geotechnical Engineer at
                                           detailed design stages.
                                           ADG have assumed saturated hydraulic conductivity of 4 × 10−6
                                           m/s which gives a yearly capacity of 3,784 𝑚3 /yr for a 30 m2
                                           bioretention infiltration area.
                                           Please see attached MUSIC modelling which shows the yearly
                                           amount of water required to be infiltrated is 2,900 𝑚3 /yr.

     5.4. Details of proposed planting     Details of proposed planting to be provided by landscape
          within he bioretention device    architect.

We believe the above responses along with the supporting information adequately addresses the items
raised in Council’s recent correspondence. Should you wish to discuss further, please feel free to contact
me on the above details.

Yours sincerely,
ADG ENGINEERS (AUST) PTY LTD


MICHAEL VAN ITALLIE
Associate Director - Civil



                                                                                                     Page 2 of 2

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.