Attachment 7A - Responses to NC Info Request by ADG
STORMWATER TREATMENT DEVICE DETAILS
4. Clarify the filter media area Refer updated SBSMP (ADG Ref: 22366 C R10 Rev04) that
proposed for the bioretention provides a preliminary section showing integration with car
device and provide a preliminary parking and surrounding.
section showing how it integrates
with the proposed car parking
and surrounding levels
5. Provide geotechnical borehole Refer geotechnical borehole and test results for neighbouring
and test results demonstrating development “Noosa Sanctuary” (Report No.
that the proposed ‘pipeless’ GEOTKPAR1178AA/A) that is included as an appendice in
bioretention will function at the ADG’s SBSMP. The bio-retention basin is likely to sit
proposed location by providing approximately 0.7m – 1.0m beneath existing surface level.
the following for the bioretention Geotech borehole logs identify a medium dense silty sand
location: (alluvial) at approximately 1.0m depth beneath existing ground
level (varies).
5.1. In-situ Soil classification
5.2. Groundwater level (BGL and The groundwater was noted at depths of 1.3m below ground
mAHD) surface level and as the subsurface profile is predominately
sands, the water table is likely to fluctuate with tides, flood and
rainfall events.
5.3. In-situ saturated hydraulic It is recommended that in-situ saturated hydraulic conductivity
conductivity test results at testing is performed during detailed design to confirm the
proposed level of bioretention modelling assumptions. Assumptions included in the SBSMP
base are that a silty sand will have a minimum hydraulic
conductivity, k, of 1.0 * 10^-8 m/s and a maximum hydraulic
conductivity of 5.0 * 10^-6. An appropriate hydraulic
conductivity has been assumed between these ranges and it is
recommended that a hydraulic conductivity and permeability
test be conducted by an experienced Geotechnical Engineer at
detailed design stages.
ADG have assumed saturated hydraulic conductivity of 4 × 10−6
m/s which gives a yearly capacity of 3,784 𝑚3 /yr for a 30 m2
bioretention infiltration area.
Please see attached MUSIC modelling which shows the yearly
amount of water required to be infiltrated is 2,900 𝑚3 /yr.
5.4. Details of proposed planting Details of proposed planting to be provided by landscape
within he bioretention device architect.
We believe the above responses along with the supporting information adequately addresses the items
raised in Council’s recent correspondence. Should you wish to discuss further, please feel free to contact
me on the above details.
Yours sincerely,
ADG ENGINEERS (AUST) PTY LTD
MICHAEL VAN ITALLIE
Associate Director - Civil
Page 2 of 2