                                                                                 Officer:            Georgina Schramm
                                                                                 Direct Telephone:   07 5329 6569
                                                                                 Our Reference:      DBW23/0030
                                                                                 Your Reference:     220297.01

               10 August 2023


               EarthCert Pty Ltd
               PO Box 432
               POMONA QLD 4568
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 8 August 2023, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              DBW23/0030

                   Street address:              27 The Anchorage, Noosaville

                   Real property description:   Lot 801 RP 910420

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Building Work Assessable Against the Planning Scheme –
                       Dwelling House within setbacks and works within 4.5m of revetment wall
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               PLANNING
                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use commencing, and then compliance maintained at all times while the use continues.




               ABN 97.969.214.121                                                                 PO Box 141
               noosa.qld.gov.au                                                            Tewantin QLD 4565
               [email protected]                                                            07 5329 6500
                                                                                                             Page 1 of 5
Document Set ID: 22535103
Version: 5, Version Date: 10/08/2023
Full text of the other 4 pages

Page 2

                      Approved Plans
               2.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.       Rev.   Plan/Document Name                                         Date

                        00.0           -      Site Plan, prepared by Paul Clout Design                   06/7/2023

                        01.0           -      Ground Floor Plan, prepared by Paul Clout Design           06/7/2023

                        02.0           -      Upper Floor Plan, prepared by Paul Clout Design            06/7/2023

                        03.0           -      Roof Plan, prepared by Paul Clout Design                   06/7/2023

                        04.0           -      Elevations, prepared by Paul Clout Design                  06/7/2023

                        05.0           -      Elevations & Section, prepared by Paul Clout Design        06/7/2023

                      Currency Period
               3.     This development approval lapses if the use has not happened by 8 August 2025, unless
                      an application to extend the currency period is approved by Council.
                      Performance Bond
               4.     Security in the form of a cash bond or trading bank guarantee to the sum of $3,000 must be
                      submitted to Council, to secure performance of all conditions of this approval, prior to the
                      issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
                      will be returned on performance of the conditions of approval less any costs incurred by
                      Council in respect of enforcing performance of this permit. Council reserves the right to call
                      upon the bond or guaranteed sum to effect compliance with conditions.
                      Noosa Waters Setback
               5.     The area within 4.5 metres of the centre line of the top of the concrete revetment wall must
                      be developed in accordance with the following:
                      a.       a minimum of 25% of the area must be planted with shrubs and small trees with a
                               mature height of 3m or less.
                      b.       a maximum of 25% of the area may be impervious, with the balance area soft
                               landscaping (i.e. grass, ground covers, shrubs and small trees).
                      c.       the ground surface within 1 metre of the revetment wall must be grass or ground cover
                               and must not include shrubs, hard pavement or artificial grass.
                      d.       any side boundary fencing must taper down to a maximum height of 1.2 metres at the
                               revetment wall and have a height not exceeding 1.5 metres at a distance of 2.25 metres
                               from the revetment wall.
                      e.       any retaining structures, planter boxes or the like must be finished with natural
                               materials such as timber or rock rather than manufactured materials.
                      Revetment Wall / Flood Storage
               6.     All works must be carried out in accordance with the approved plans and Reference
                      Document No. 221281 prepared by Lindsay Consulting Pty Ltd dated 14 June 2023.
               7.     Certification of the completed works within the 4.5m setback from the revetment wall must
                      be submitted to Council within 3 months of the completion of the works. The certification must
                      be prepared by a RPEQ (Registered Professional Engineer of Queensland) and state that
                      the works:



                                                                                                        Page 2 of 5
Document Set ID: 22535103
Version: 5, Version Date: 10/08/2023

Page 3

                      a. have not negatively impacted the stability of the revetment wall or negatively impacted
                         the associated membrane;
                      b. have not reduced the available flood storage within the lot from the profile as described
                         in The Noosa Plan 2020 – Low Density Residential Zone Code; and
                      c. be generally in accordance with Water Volume Calculations (22-0813-F1 and F2
                         Revision A) prepared by Lindsay Consulting Pty Ltd.
               5.     REFERENCE DOCUMENTS

                Plan No.               Rev.   Plan/Document Name                                 Date

                221281                  -     Flood Calculations Letter - Prepared by Lindsay 14 June 2023
                                              Consulting Pty Ltd

                22-0813-F1              A     Water Volume Calculations, Sheet 1 – Prepared by 13 June 2023
                                              Lindsay Consulting Pty Ltd

                22-0813-F2              A     Water Volume Calculations, Sheet 2 – Prepared by 13 June 2023
                                              Lindsay Consulting Pty Ltd

               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required             Subject of the required Development Permit

                Development Permit for Building Works           All building work.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If


                                                                                                     Page 3 of 5
Document Set ID: 22535103
Version: 5, Version Date: 10/08/2023

Page 4

               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.

               Yours faithfully,




               Georgina Schramm
               Development Planner


               Enc:   Appeal Rights
                      Approved Plans/Documents




                                                                                                      Page 4 of 5
Document Set ID: 22535103
Version: 5, Version Date: 10/08/2023

Page 5

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 5 of 5
Document Set ID: 22535103
Version: 5, Version Date: 10/08/2023

Used in these records

About this file

File size
143 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

ECM_22535103_v5_Decision Notice - DBW23 0030.pdf · 143 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.