GENERAL COMMITTEE MEETING AGENDA 13 FEBRUARY 2023
Page 44 of 70
GENERAL COMMITTEE MEETING AGENDA 13 FEBRUARY 2023
Corporate Plan Theme - The Noosa Community Operational Plan 22/23
Corporate Plan Key Operational Initiatives Outcomes Responsible Areas Update Q2 Status
Focus Areas
2.3 Implement the | New Mobile Library and Accessible and contemporary outreach library | Libraries Peregian Beach and Pomona Kiosks Behind
Libraries Strategic Community Outreach services installed and operational. Vehicle Tender Schedule
Plan Service is implemented awarded in July 2021 -delivery delayed due
to supply chain issues. Proposed delivery
date February 2023. Fit Out required
before launching to community.
Outreach programs continue and are
increasing in popularity.
2.4 Continue to Progress the implementation | Strategic direction for the development and Community NDSC pathways and roads Civil project is | On track
support our of the Master Plans for the implementation of sport and recreation facilities | Facilities awaiting new grant funding options post
community to Noosa District Sports BBRF funding ceasing.
utilise Council Complex and Cooroy Sports ReGen project feasibility study still
controlled land and | Complex progressing with LMP also being
buildings through undertaken, with consultant to be present
formal tenure draft report early in new year.
arrangements MacKinnon Drive project progressing,
tender awarded.
Cooroy Sports Complex has some
preliminary concept designs done and
currently working through development
approval process.
Noosa Leisure Centre Optimization of the use of the facility and Community Contract awarded to Otium Planning Group,| On track
Options Study community needs are met Facilities stage 1 of Needs Assessment and
stakeholder engagement to start in new
year.
Wallace House Wood Borer | Preventative maintenance to ensure the Property Branch Discussing scheduling options with Completed
inspection structural integrity of the building resident group.
Repaint Peregian Beach Surf | Preventative maintenance to ensure the whole | Property Branch Painting completed. Completed
Clubhouse of life structural integrity and amenity of the
building
2.5 Plan and build All-Abilities Playground Increased interaction and inclusiveness making | Infrastructure Playground opened in May 2022. Completed
Page 44 of 70See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.