1. APPLICATION DETAILS
Application No: OPW20/0114
Street address: Portside Noosa Waters 1/4 Portside Ct Noosaville Qld 4566
Portside Noosa Waters 2/4 Portside Ct Noosaville Qld 4566
Real property description: Lot 1 BUP 103414 and Lot 2 BUP 103414
Planning Scheme: The Noosa Plan (8 June 2018)

2. DECISION DETAILS

The following type of approval was issued:
° Development Permit for Operational Works — Jetty

3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
j 4. CONDITIONS OF APPROVAL

Approved Plans

1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.

Plan No. Rev. —_ Plan/Document Name Date

20.046 Sheet lof2 E Site Plan prepared by Kunkel Building Design , 6 August 2020
Sheets

20.046 Sheet 20f2 E Floor Plan, Floor Framing Plan & Typical Section 6 August 2020
Sheets " prepared by Kunkel Building Design

Currency Period

2: The development approval lapses if the works have not been completed and all conditions of
approval been complied with by 20 May 2023, unless an application to extend the currency
period is approved by Council.

Site Specific Conditions

3. The approved plans must be certified by a suitably qualified Registered Professional Engineer
of Queensland (RPEQ) as being suitable for the intended use prior to the commencement of
construction. A copy of the certified plans must be submitted to Council for records purposes

4. The Registered Professional Engineer of Queensland (RPEQ) bears full responsibility for all
structural aspects of the jetty.

General Conditions

5. All structures must be designed and constructed such that they are free standing within the
waterway and are not connected to or behind the revetment wall

6. All structures must have no detrimental effects on stormwater drains and/or easements.

7. Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the top of the
revetment wall.

8. Arigid handrail must be fitted on one side of the walkway.

9. No posts or vertical supports of the proposed jetty are to extend vertically from the structure
unless they provide necessary support for the handrail.

No boatlifting devices are to be attached or moored at the jetty structure for the purpose of
elevating a vessel above the water without Council approval.

 
Log in to download the original file

Court Judgement 10 Jun 2021 - Case 209 of 2020.pdf · 436 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.