Development Application Part 2 of 3 Report MCU13/0106

of 54

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (27.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

                                                                                                                                                                                               16



Attachment B     -
                   Assessment Against Natural Hazards Overlay Code


      13.30.2 The overall outcomes sought from the Natural Hazards Overlays Code are-


      a) development in areas at risk from natural hazards is compatible with the nature of the natural hazard;
      b) the risk to people, property and the natural environment from natural hazards is minimised;
      c)development does not result in a material increase in the extent or severity ofnatural hazards; and
      d) for acid sulfate areas-the generation or release of acid and associated metal contaminants into the environment is avoided

13.31 Specific outcomes for the Natural Hazards Overlay Code
The specific outcomes sought for the Natural Hazards Overlay Code are included in column 1 of Tables 13.8-13.12. Acceptable solutions for self-assessable development and probable
solutions for code assessable development are included in column 2 of Table 13.8-13.12.


Table 13.8 Landslide hazard areas


Specific Outcomes                                            Probable Solutions                                              Assessment                                               Compliance
13.32 Effects of use
General
01 Development is located to ensure it does not              S1.1 The proposed development is not located in a landslide     The site is well vegetated and there is no evidence of
compromise the safety of people, property               or   hazard area as indicated on Overlay Maps OM1.3-0M9.335;         any land slippage      (Refer geotechnical report
hazardous materials manufactured or stored in bulk           OR                                                              Attachment C).
by increasing risk oflandslide;                              S1.2 The development site is not subject to landslide, either
                                                             intemally or from sloping land above the site (ego slopes are   During construction of the lower level, a maximum cut
AND                                                          less than 1 in 10"(10%)                                         depth of 1.5 m is estimated to the westem edge of
                                                             AND                                                             the lower pad at which point an engineer certified
02 Development, including accessways is designed             S1.3 Development, including necessary earthworks within         block retaining wall will form part of the westem wall
and constructed to-                                          Precinct F of the Noosa Springs site, improves the stability of of the lower building level. The excavated cut will be
a) minimise impacts on the natural landform;                 any non-natural landform so it is not at risk from landslide back filled to the engineer’s recommended level.
b) minimise risk to people and property from                 either on the site or from sloping land above the site.
    landslide;                                                                                                               A proposed buffer zone between the neighbouring
c) avoid any potential instability and associated            S2.1 No solution provided                                       dwelling to the south of the ground floor
   problems, including long term stability of the site
   and long term stability ofthe development.
Protection of Infrastructure and Community Uses
03Community Uses and Infrastructure Uses,                    S3.1 Community Uses and Infrastructure Uses are not
including that identified below, are able to function        located in a landslide hazard area as indicated on Overlay
effectively during and immediately after landslide           Maps OM1.3- OM9.3;

Used in these records

About this file

File size
27.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application Part 2 of 3 Report MCU13_0106.pdf · 27.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.