Appendix I - Bushfire

Attached to the e-mail Multiple Housing Type 3 Retirement & Special Needs (48 units) - MCU18/0009.

of 17

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                            RF&A

                                    Rob Friend & Associates Pty Ltd
                                        Environmental Land Management Consultants
                                 ABN 83 097 068 114                                    28 Merton Road
                                 ACN 097 068 114                              Woolloongabba Qld. 4102
                                                                                     p - (07) 3891 9131
                                                                                      m - 0419-667346
                                                                             e - [email protected]

Your reference –
Our Reference – RF17-020
5 December 2017

Carramar Care – Tewantin
c/- Peter Middap
Middap Architecture
PO Box 1352
Noosaville, Qld 4556

Dear Peter,

Re: Bushfire Hazard Statement – Carramar Care, 186 Cooroy Noosa Road,
Tewantin
Rob Friend & Associates Pty Ltd has been asked to undertake an assessment of the bushfire hazard issues
relative to the proposed development application for the above site.

A site inspection was undertaken on the 15 June 2017 to ascertain the validity of the bushfire hazard mapping
over the property and adjacent properties as mapped in the Noosa Plan Natural Hazard Overlay Code (16
September 2013).

Development proposal

Carramar Care is proposing to lodge a Material Change of Use (MCU) application with Noosa Council to allow for
construction/expansion of a Dementia unit at the current facility at 186 Cooroy Noosa Road, Tewantin. The
development is proposing the construction of a further 7 buildings, consisting of 6 villas with 8 resident rooms per
villa, and an Entry Building which will contain a café as well as dining and resident facilities in the western portion
of the development footprint (see Figure 1).

We note, the current, proposed layout plan considers a setback of 14.1 metres as recommended and all
proposed structures allow for this setback.

The subject site currently consists of trees and regrowth vegetation (see Photographic Plate 2); however most of
this will be cleared for the development. A small portion of the existing vegetation will be retained, mostly a small
patch to the south of the existing Cartwright South building.
Log in to download the original file

Appendix I - Bushfire.pdf · 523 KB (small file)

Full text of the other 16 pages

Page 2

                                                      [2]




Figure 1 – Proposed Development Plan

Site description

       The subject site is located at 186 Cooroy Noosa Road, Tewantin and is described as Lot 2 on
        RP177554, covering an area of 4.047 hectares (see Figures 2).
       The site is zoned as Community Services under the Noosa Plan Zones.
       The subject site is approximately 0.80 hectares in area and is east of the existing Dementia unit, which
        was completed sometime in 2013.
       To the north of the subject site are residential properties (see Photographic Plate 3), and the southern
        boundary of the site is bordered by Cooroy Noosa Road. Across the Cooroy Noosa Road and further to

Page 3

                                                       [3]


        the south of the site is Tewantin National Park – Wooroi Day Use Area (see Photographic Plate 1),
        which includes a maintained, powerline easement and several internal, recreational tracks (see
        Photographic Plate 5). We note the vegetation of the Wooroi Day Use Area close to the road and
        powerline easement has been burnt within the last 3 years (see Photographic Plate 6).
       West of subject site consists of a vegetated, waterway corridor, Lomandra Place Bushland Reserve
        (see Photographic Plate 4), which contains a degraded woodland canopy of Paperbark teatree,
        Melaleuca quinquenervia Swamp box, Lophostemon suaveolens and Black sheoak, Allocasuarina
        littoralis with an understorey dominated by a range of environmental weed species such as Umbrella
        tree, Schefflera actinophylla, Singapore daisy, Sphagneticola trilobata in the eastern and central
        portions.
       In addition, Lomandra Place Bushland Reserve also contains a waterhole which occupies a significant
        portion of the width of the park toward the western end of the Park.
       We did note the western portions of the Lomandra Place Bushland Reserve and the area within the
        subject site, appears to have less disturbance from environmental weeds and contains more an
        understorey and groundcover consistent with coastal paperbark wetlands.
       We also noted, Lomandra Park nor the vegetated portion of the Carramar Noosa site is not mapped as
        remnant vegetation. Furthermore, the area is also not mapped as remnant in the latest version 10
        Regional ecosystem mapping over South-east Queensland or Bioregion 12.




Figure 2 – Aerial image

The Noosa Plan (2013)

       The Noosa Plan (2013) Natural hazards overlay map does not map any areas within the subject site nor
        the adjacent Lomandra Place Bushland Reserve as being a Bushfire hazard area. we note under the
        State Planning Policy – Natural Hazards, Risk and Resilience – Technical Manual corridors of
        vegetation less than 100 metres can be mapped in accordance with the dominant adjacent bushfire
        hazard class and as the adjacent areas are mapped as Low bushfire hazard, the waterway corridor is
        also mapped as an area of Low bushfire hazard.
       The Noosa Plan does however map the vegetation in the Tewantin National Park to the south of the site
        and a small portion to the south west of the site as Very high potential bushfire Intensity (see Figure 3).

Page 4

                                                       [4]


        As a consequence, the 100-metre-wide Potential impact buffer extends over more than half of the
        southern portion of the site.
       As the site is affected by area mapped as Very high potential bushfire hazard and the Potential impact
        buffer, a response to the Natural Hazards Overlay Code is required (see Attachment I below).
       The Noosa Plan also maps this area as an Environmental Protection Area under the Biodiversity
        overlay.




Figure 3 – Noosa Plan - Bushfire Overlay Map

Bushfire Hazard Assessment

Methodology

       An assessment of the bushfire hazard was undertaken using a desktop review. Resources such as
        historic and current aerial photography, Google street view images, the Noosa Plan (2013) and the
        State Planning Policy (April 2016) Natural Hazards, Risks and Resilience Bushfire Hazard Mapping
        were used as part of the desktop analysis.
       A site inspection was undertaken to identify the status of vegetation within and around the site and to
        determine the likelihood of a bushfire on the site presenting risk to life and property.

Findings

       With respect to the existing vegetation on the subject site and to the west of the subject site, we
        observed the following: -
         Melaleuca quinquenervia, Eucalyptus microcorys, Eucalyptus robusta, Syncarpia glomulifera,
            Cinnamomum camphora (w), Lophostemon suaveolens, Livistona australis, Syzygium smithii,
            Endiandra sieberi, Acacia maidenii, Macaranga tanarius, Alphitonia excelsa, Allocasuarina littoralis,
            Elaeocarpus reticulatus, Melaleuca linariifolia, Syagrus romanzoffiana (w), Glochidion ferdinandi,
            Cryptocarya longifolia, Schefflera actinophylla (w), Senna pendula var. glabrata (w), Breynia
            oblongifolia, Hovea longifolia, Lantana camara (w), Cordyline rubra, Lophostemon polygalifolia,

Page 5

                                                            [5]


                Nephrolepis cordifolia (w), Gleichenia dicarpa, Stephania japonica, Zieria sp. Smilax australis,
                Gahnia sieberiana, Blechnum indicum, and Sphagneticola trilobata (w).
           The eastern portion of the waterway corridor is entirely invaded by Sphagneticola trilobata across
                the width of the waterway (see Photographic Plate 7). This will have a significant effect on the
                ability of any fire commencing within the waterway corridor/Reserve
         With respect to the areas mapped as potential bushfire hazard in the Noosa Plan Natural Hazards
          Overlay Mapping we make the following comments: -
           We confirm the vegetation of the Tewantin National Park is correctly mapped as Very High potential
                bushfire intensity based on the mapped Vegetation hazard class (8.1 – Wet eucalypt tall open
                forest) and the FFDI over the area (FFDI – 47). However, we do note the bushfire hazards within
                this section of the Tewantin National Park are managed by way of controlled burns and as such the
                actual bushfire hazard presented by the understorey is significantly lees than the Potential bushfire
                hazard level derived from the State based bushfire hazard data.
         The subject site is separated from the Tewantin National Park by a distance of approximately 50+
          metres due to the Cooroy Noosa Road and area on the road shoulder, and a bikeway which are also
          maintained in a relatively clear state (see Photographic Plate 1).
         Lomandra Place Bushland Reserve is less than 100 metres in width and can be deemed to be
          considered the same bushfire hazard as the surrounding properties, as per State Planning Policy –
          Natural hazards, Risk and Resilience – Technical manual. The Lomandra Place Bushland Reserve is
          surrounded by areas of Low bushfire hazard.
         Access into and away from the proposed facility will be provided by the Cooroy Noosa Road which has
          two-way access allowing staff, residents and emergency services to approach the site from the direction
          of Tewantin or Cooroy.
         Additionally, the proposed dementia facility will also utilise the existing internal vehicle access routes
          which will provide vehicle and Emergency Service access to the northern boundary as well as the
          southern boundary. In additional Emergency vehicle access will also be available to each residential
          villa via the proposed internal pedestrian tracks. It is acknowledged however that should the facility be
          involved in a structural fire, Emergency Service may park close to a hydrant stand pipe and undertaken
          fire suppression operations via extend hoses.
         With regard to a vegetation fire, again the internal roadways and access tracks will facilitate rapid access
          throughout the facility to protect buildings and if required, directly attack the fire when it is in proximity to
          the facility.
         With respect to potential evacuation, there are ample resident community space available within the
          existing facility that can be used as a temporary evacuation area and where residents can be care for
          until they are able to return to their respective rooms once emergency service give the all clear to do so.

Discussion

Bushfire hazard mapping

Further to our findings above and based on the vegetation types and therefore the Vegetation hazard classes as
described by Leonard et al (2014)1 we have come to the view that: -

         With respect to the vegetation of Tewantin National Park to the south of the site it presents as a bushfire
          hazard:
              o We acknowledge the State Government’s Regulated Vegetation Management Mapping maps
                   the National Park as Regional ecosystem 12.5.6c - Eucalyptus pilularis open forest +/- E.
                   siderophloia, E. propinqua, Corymbia intermedia, E. microcorys, E. acmenoides, E.
                   tereticornis, E. biturbinata, Lophostemon confertus with E. saligna, E. montivaga at higher
                   altitudes. Occurs on remnant Tertiary surfaces. Usually deep red soils. (BVG1M: 8b).


1 Ibid.

Page 6

                                                            [6]


              o    We generally agree with the State’s mapping with regard to the regional ecosystem throughout
                   this section of Tewantin National Park, however the area adjacent to the subject site is more
                   open and contains a relatively depauperata understorey and groundcover, and as such, is
                   better described as a moist to dry eucalypt forest on coastal lowlands and ranges i.e. VHC 9.1.
                   This area contains largely low to moderately flammable vegetation (see Photographic Plate 6)
              o Table 1 below provides the derived Potential bushfire intensity level using the methodology
                   after Leonard et al (2014)2 and as contained in the State Planning Policy – Natural Hazards,
                   Risks and Resilience – Technical Manual – A fit for Purpose approach in undertaking natural
                   hazard studies and risk assessment (April 2016)
         With respect to the vegetation of the subject site and waterway corridor to the west of the site, it is
          evident that it presents as a Low Bushfire Prone Area largely because of its width:
              o The site inspection revealed there was an extensive invasion Sphagneticola trilobata in the
                   north eastern portion and a dam in the centre of the waterway corridor
              o We note that a large amount of vegetation within the subject site will be cleared as a natural
                   consequence of the development
              o Table 2 below provides an assessment of the status of the bushfire hazard without any
                   management input and as if the area was a melaleuca open forest with all the structural
                   elements and characteristics of that forest. However, in accordance with Leonard et al (2014)
                   section 2.2.1 – Patch and Corridors,3 the waterway corridor and retained portion of vegetation
                   in the south of the subject site will be less than 100 metres in width and as such using the
                   State Planning Policy methodology this can be effectively described as low bushfire hazard like
                   the surrounding properties.

Table 1 – Fireline Intensity Model data for adjacent area of the Tewantin National Park

Characteristic                                                    Input/output value
Vegetation hazard class                                           9.1 Moist to dry eucalypt open forests on coastal
                                                                  lowlands and ranges1
Potential fuel load (t/ha)                                        24.12
FFDI                                                              473
Slope (degrees)                                                   2
Potential fireline intensity (kW/m)                               19,429
Potential Bushfire Hazard Class                                   Medium
1 – the VHC 9.1-Moist to dry eucalypt open forests on coastal lowlands and ranges was used as it is representative of RE
12.5.6c and what we observed.
2 – the Potential fuel load is attributed with a potential fuel load by the State Government as part of the Leonard et. al.
(2014) methodology.
3 – the FFDI for the area is determined by the State Government as part of the Leonard et. al. (2014) methodology.

Table 2 – Fireline Intensity Model data for Subject Site and Waterway Corridor

Characteristic                               Input/output value
Vegetation hazard class                      22.1 Melaleuca open forests on seasonally inundated lowland coastal
                                             swamps1
Potential fuel load (t/ha)                   28.42
FFDI                                         473
Slope (degrees)                              2
Potential fireline intensity (kW/m)          26,981



2 Ibid.
3 Ibid.

Page 7

                                                            [7]


Characteristic                               Input/output value
Potential Bushfire Hazard Class              High
1 – the VHC 22.1-Melaleuca open forests on seasonally inundated lowland coastal swamps was used because
2 – the Potential fuel load is attributed with a potential fuel load by the State Government as part of the Leonard et. al.
(2014) methodology.
3 – the FFDI for the area is determined by the State Government as part of the Leonard et. al. (2014) methodology.

         We also acknowledge that while the Lomandra Place Bushland Reserve is an area of low bushfire
          hazard, it may become involved in a bushfire event and as such needs to achieve a separation from that
          vegetation necessary to achieve the radiant heat flux of 19kW/m2.
         Table 3 provides the outputs for potential setbacks from the retained vegetation. We acknowledge the
          age and vulnerability of the residents using the proposed development and recommend that the setback
          should achieve a lower radiant heat level than necessary for the residents.

Table 3 – Minimum Distance Calculations

186 Cooroy Noosa Road, Tewantin - Minimum Distance Calculator - AS3959-2009 (Method 2)
                        Inputs                                                       Outputs
 Fire Danger Index               42                    Rate of spread                          0.81 km/h
 Vegetation classification       Woodland              Flame length                            8.62 m
 Surface fuel load               15 t/ha               Flame angle                             54 °, 65 °, 74 ° & 79 °
 Overall fuel load               28 t/ha               Elevation of receiver                   3.24 m, 3.57 m, 3.65 m &
                                                                                               3.51 m
 Vegetation height               n/a                   Fire intensity                          11,718 kW/m
 Effective slope                 1°                    Transmissivity                          0.863, 0.849, 0.827 & 0.803
 Site slope                      2°                    Viewfactor                              0.6056, 0.447, 0.3007 &
                                                                                               0.2043
 Flame width                   100 m                     Minimum distance to < 40 kW/m²        7m
 Windspeed                     35 km/h                   Minimum distance to < 29 kW/m²        9.5 m
 Heat of combustion            18,600 kJ/kg              Minimum distance to < 19 kW/m²        14.1 m
 Flame temperature             1,090 K                   Minimum distance to < 12.5 kW/m²      20.5 m
1. Rate of Spread - Mcarthur, 1973 & Noble et al., 1980
2. Flame length - NSW Rural Fire Service, 2001 & Noble et al., 1980
3. Elevation of receiver - Douglas & Tan, 2005
4. Flame angle - Douglas & Tan, 2005
5. Radiant heat flux - Drysdale, 1999, Sullivan et al., 2003, Douglas & Tan, 2005

Conclusion

Based on the above findings and discussions it is our opinion that: -

      1. The bushfire hazard mapping of the Tewantin National Park can effectively be mapped as an area of
         medium bushfire hazard based on the particular vegetation assemblage within the area adjacent to the
         subject site.
      2. A 100-metre-wide Potential impact buffer still extends over more than half of the subject site.
      3. Although the waterway corridor and the retained vegetation on the site are considered an area of Low
         bushfire hazard in accordance with the Patch and Corridor mapping methodology as per section 2.2.1,

Page 8

                                                           [8]


              Leonard et al (2014),4 given the age and vulnerability of the residents using the proposed development
              the bushfire hazard planning for this vegetation will need to consider these aspects.

Recommendations

The following recommendations have been made with respect to mitigating against the external bushfire hazards
as part of this development:

          1. All buildings to be set back from retained vegetation by at least 14.1 metres to ensure the maximum
             exposure to a bushfire event is 19kW.m2 as determined using Method 2 in AS3959-2009 (see Figure
             1).
          2. All buildings to be constructed to a minimum BAL-19 standard as provided by the Australian Standard
             AS3959-2009.
          3. The understorey within the 14.1 metre setback be removed and maintained as groundcover less than
             200 mm in height.
          4. All trees which have branches that extend closer than 5 metres to any structure be trimmed or if an
             Arborist is of a view the trimming would destabilise the tree then it be removed.
          5. Retained vegetation required to be maintained by regular maintenance particularly prior to the bushfire
             season in South-east Queensland, September to December.
          6. The construction of a 2.5-metre-high non-flammable fence is to be constructed along the eastern
             boundary of the site. We note the likelihood that there would be a significant need for ground dwelling
             fauna movement between the subject site and Lomandra Place Bushland Reserve is low and as such
             there may not be any requirement to allow for fauna movement under or around the fence.
          7. Vehicular access to be provided around buildings to enable access for Emergency Services.
          8. The facility be connected to reticulated water and a hydrant standpipe be located in the northern and
             central parts of the proposed development area to allow rapid access for reticulated water by
             Emergency services for structural and vegetation fires.
          9. If an emergency response plan has not been produced or has not been reviewed within the last 5
             years, it be reviewed or if none exists, one be prepared, to provide clear and concise instructions and
             response for staff and residents should a bushfire event threaten the site. we note the main threat will
             be from smoke rather than direct flame attack.

If you have questions about this letter, please do not hesitate to contact us by phone or email. I have also
attached a copy of our Business Profile for your information.

Kind regards,




Rob Friend
Director
Rob Friend & Associates




4 Ibid.

Page 9

Response to the Natural Hazard Overlay Code – Table 13.9

Specific Outcomes                                                   Probable Solutions                                                Response
Effect of Use and Works
New Uses                                                            S4.1                                                              R4
                                                                                                                                       The proposed development footprint is not in an area of
O4                                                                  The use is sited on land that is not in a Bushfire Hazard Area,
                                                                                                                                         mapped bushfire hazard. However, a potential impact
                                                                    OR
The proposed use does not compromise the safety of people                                                                                buffer extends to part of the area within which the
or property from bushfire.                                          S4.2                                                                 proposed development is to occur.
                                                                                                                                       A setback has been proposed to ensure the buildings
                                                                    The use is sited on land that is determined as low bushfire
                                                                    risk by a site specific bushfire hazard assessment                   are only exposed to a maximum radiant heat flux of
                                                                                                                                         19kW/m2.

Protection of Infrastructure and Community Uses                     S5.1 Community Uses and Infrastructure Uses are not               R5
O5                                                                  located in Bushfire Hazard Area ;
                                                                                                                                          While the site is zones as “Community Areas” under the
Community Uses and Infrastructure Uses, including that
                                                                    OR                                                                     Noosa Plan Zones, the proposed development is not
identified below, are able to function effectively during and
                                                                                                                                           defined as a “community use” in the Noosa Plan
immediately after bushfire events—                                  S5.2

a)   Emergency service facilities;                                  Building work will not involve more than an additional 20m2 of
b)   Hospitals;                                                     gross floor area to an existing building;
c)   Education Type 4 uses, including stores for valuable
                                                                    OR
     records or items of historic or cultural significance; and
d)   Service and utility uses, including electricity substations,   S5.3
     major electrical depots and water treatment plants             Where located in a Bushfire Hazard Area, uses are designed
                                                                    to function effectively during and immediately after bushfire
                                                                    events and have direct access to low hazard evacuation
                                                                    routes
Hazardous materials                                                 S6.1                                                              R6.1
O6                                                                  Hazardous materials are not manufactured and stored                   The development will not manufacture or store
                                                                    in a Bushfire Hazard Area.                                             excessive amounts of Hazardous materials. Its
Public safety and the environment are not adversely
                                                                                                                                           primary use will be for the treatment and housing of
affected by the detrimental impacts of bushfire on
                                                                                                                                           Dementia patients.
hazardous materials manufactured or stored in bulk.

Page 10

                                                                                              [10]


Specific Outcomes                                                Probable Solutions                                                 Response
Siting, design and construction
O7                                                               S7.1                                                               R7.1
Uses and works including building works are sited, designed      Uses and works including building works are sited—
                                                                                                                                          The site is greater than 2,500 sq.m. in area.
and constructed to—
                                                                 a)   on lots greater than 2500m2;                                        The proposed development footprint is located in an area
a)   minimise the number of people and property subject to            i.    in locations of lowest hazard within the lot (Figure           of Low bushfire hazard, however parts of the
     bushfire risk; and                                                     13.5 is omitted for convenience); and                          development is located within a Potential impact buffer.
b)   maximise the protection of people and property during           ii.    to achieve setbacks from hazardous vegetation of              While the nominal width of a Potential impact buffer is
     the passage of a fire front.                                           1.5 times the predominant mature canopy tree                   100 metres, the buildings will be setback from the area of
                                                                            height or 10m whichever is the greater; and                    medium bushfire hazard (as determined in this report) by
                                                                    iii.    10m from any retained vegetation strips or small               a distance of greater than 50 metres.
                                                                            areas of vegetation; and                                      Base don the management undertaken within the
                                                                    iv.     so that the elements of the development least                  Tewantin National park by Queensland Parks and
                                                                            susceptible to fire are sited closest to the bushfire          Wildlife Service, the adjacent area and its inherent fuels
                                                                            hazard;                                                        are managed and as such it is unlikely that a significant
                                                                 b) on lots 2500m2 or less - to maximise setbacks from                     bushfire would involved the vegetation within the
                                                                      hazardous vegetation                                                 Tewantin national park and threaten the buildings of
                                                                                                                                           residents or staff within the Carramar Care facility.
Water supply for fire fighting
O8                                                               S8.1                                                               R8.1
An adequate and accessible water supply is provided for fire     For premises not in a water service area— each lot has an                The development is in a water service area.
fighting purposes can be accessed by fire fighting appliances.   accessible dam, swimming pool or water tank accessible by
                                                                 the fire brigade that contains at least 5000 litres of water
Vehicle access and fire trails
Firebreaks and fire access tracks                                S9.1                                                               R9.1
O9                                                               Firebreaks are provided by—                                              The proposal is for 6 residential villas and as such the
                                                                                                                                           area around the villas will be open allowing access for
Firebreaks or fire access tracks provide—                        a)     a cleared road reserve not less than 20m wide located
                                                                                                                                           Emergency Services to each building.
                                                                        around the perimeter of the development;
a)   adequate access for fire fighting and other emergency                                                                                A proposed setback from the area of retained vegetation
     vehicles; and                                               OR                                                                        within the Lomandra Place Bushland Reserve of 14.1
b)   adequate width to minimise the risk of fire crossover.                                                                                metres. While this setback will not be suitable for vehicle
                                                                 b)     fire access tracks between the development and
                                                                                                                                           movement, vehicle movement is available to the
                                                                        surrounding vegetated lands that—

Page 11

                                                                                                 [11]


Specific Outcomes                                                    Probable Solutions                                              Response
                                                                           i.    are a minimum cleared width of 6m;                      northern, central and southern portions of the
                                                                           ii.  have a maximum grade of 1 in 8 (12.5%);                  development footprint.
                                                                           iii. have a formed pavement;
                                                                           iv.  have access at each end and in other locations
                                                                                where necessary;
                                                                           v. have passing areas and turning areas;
                                                                           vi. have clearly identified access points for emergency
                                                                                vehicles; and
                                                                           vii. are located on public land or within access
                                                                                easements that are granted in favour of the Noosa
                                                                                Council and the Queensland Fire and Rescue
                                                                                Service.
Reconfiguring a Lot
General                                                              S10.1                                                           R10.1
O10                                                                  The proposed lots are not located on land that is subject to       The proposed development area is not mapped as a
                                                                     Bushfire Hazard                                                     bushfire hazard area, however a Potential impact buffer
The safety of people and property are maintained by
                                                                                                                                         covers part of the development footprint.
                                                                     OR
a)    Locating house site areas and other sensitive uses on                                                                             An assessment of the separation distance from the
      that part of the land least affected by the bushfire           S10.2                                                               hazardous vegetation within the Tewantin national park
      hazard; and                                                                                                                        indicates the separation of the closest buildings to the
                                                                     The proposed lots are sited on land determined as low
b)    fire mitigation methods are used that are adequate for                                                                             hazardous vegetation is approximately 50 metres and
                                                                     bushfire risk by a site specific bushfire hazard assessment
      the Potential Bushfire Hazard rating of the individual site,                                                                       that this separation contains a formed roadway, Cooroy
      having regard to –                                             AND                                                                 Noosa Road which allows for two-way access into and
        i. vegetation type;                                                                                                              away from the site.
                                                                     S10.3
        ii. slope;                                                                                                                      This access is not through an area mapped as a bushfire
        iii. aspect;                                                 Additional lots are not created where their only vehicular          hazard area, however the access is within a potential
        iv. on-site and off-site fire hazard implications of the     access route is through a Bushfire Hazard area                      impact buffer.
             development;
        v. bushfire history;
        vi. conservation values of the site; and
        vii. ongoing maintenance

Page 12

                                                                                           [12]


Specific Outcomes                                              Probable Solutions                                              Response
Firebreaks and fire access tracks                              S11.1                                                           R11.1
O11                                                            Firebreaks are provided by—                                        The proposal is not for a sub-division, however access
                                                                                                                                   for Emergency Services is provided via existing internal
Firebreaks or fire access tracks provide—                      a)   a cleared road reserve not less than 20m wide located
                                                                                                                                   road network as well as access through parts of the
                                                                    around the perimeter of the subdivision, between the
a)    adequate access for fire fighting and other emergency                                                                        proposed development area for both structural and
                                                                    created lots and surrounding vegetated lands;
      vehicles; and                                                                                                                vegetation fire suppression operations.
b)    adequate width to minimise the risk of fire crossover.   OR
                                                               a)   fire access tracks (may be in the form of an access
                                                                    easement) between the created lots and surrounding
                                                                    vegetated lands that—
                                                                      i. are a minimum cleared width of 6m;
                                                                      ii. have a formed pavement;
                                                                      iii. have access at each end and in other locations
                                                                           where necessary;
                                                                      iv. have passing areas and turning areas;
                                                                      v. have clearly identified access points for emergency
                                                                           vehicles; and
                                                                      vi. are located on public land or within access
                                                                           easements that are granted in favour of the Noosa
                                                                           Council and the Queensland Fire and Rescue
                                                                           Service

Road network                                                   S12.1                                                           R12.1
O12                                                            Cul-de-sacs or no-through roads are not used in the street         The development will depend on the existing internal
                                                               network unless—                                                     road network as well as additional access for internal
Roads provide for the safe and effective evacuation of users
                                                                                                                                   movement of residents should a bushfire potentially
of premises and access by Emergency services.                  a)   a perimeter road reserve with a minimum reserve width
                                                                                                                                   impact on residents. This impact is likely to be restricted
                                                                    of 20m and a formed width of not less than 6m is
                                                                                                                                   to smoke rather than direct flame attack.
                                                                    provided; or
                                                               b)   cul-de-sacs or no-through roads are provided with fire
                                                                    trails or access easements, capable of being navigated
                                                                    by conventional vehicles, that link to through roads

Page 13

                                                                                            [13]


Specific Outcomes                                              Probable Solutions                                                 Response
                                                                     (Figures 13.3 and 13.4 omitted);
                                                               AND
                                                               S12.2
                                                               Roads have a maximum grade of 1 in 8 (12:5%).
Lot design                                                     S13.1                                                              R13.1
O13                                                            Each residential lot—                                                 the development proposal is not for a Sub-division but for
                                                                                                                                      the development of a residential dementia care facility to
Lot design and building siting minimises bushfire hazard to    a)    includes a house site area, identified on the plan of
                                                                                                                                      increase the capacity of the existing Cartwright Village.
people and property having regard to slope, aspect, existing         subdivision;
                                                                                                                                     The proposed residential villas, will achieve a separation
vegetation and adequate separation from hazardous              b)    is of sufficient size and dimensions to accommodate a
                                                                                                                                      from existing hazardous vegetation to the south of the
vegetation.                                                          dwelling and ancillary buildings and use areas;
                                                                                                                                      facility of greater than 50 metres and to areas of low
                                                               c)    for lots more than 2,500m—
                                                                                                                                      bushfire hazard/retained vegetation of 14.1 metres.
                                                                      i. conform with the principles for house site numbers
                                                                            1, 2 or 3 shown in Figure 13.5 (omitted); and         R13.2
                                                                      ii. are separated from hazardous vegetation for a
                                                                                                                                     The existing internal road network and new pedestrian
                                                                            distance the minimum of 1.5 times the
                                                                                                                                      pathways will continue to provide suitable access for
                                                                            predominant mature canopy height or 10m,
                                                                                                                                      Emergency Services to access the proposed structures
                                                                            whichever is the greater; and
                                                                                                                                      for both structural fires and to attack vegetation fires
                                                               d)    for lots less than 2,500m2, maximise separation of
                                                                                                                                      within areas of retained vegetation to the east of the
                                                                     buildings from hazardous vegetation.
                                                                                                                                      proposed development footprint.
                                                               S13.2
                                                               Residential lots are designed so that their size and shape
                                                               allow for efficient emergency access to buildings for fire
                                                               fighting appliances (e.g. by avoiding long narrow lots with long
                                                               access driveways).

Page 14

                                              [14]


Photographic plates




       Subject Site


                                                                             Tewantin National
                                                                                  Park

                                                                  50+ m




Photographic Plate 1 – view of the subject site from the south showing the separation
distance between Tewantin National Park and the subject site.




Photographic Plate 2 – view of the existing drainage line within the subject site.

Page 15

                                            [15]




Photographic Plate 3 – view of the northern boundary of the subject site showing residential
properties to the north off Spey Court.




Photographic Plate 4 – view of western boundary fence of subject site and the vegetated
waterway corridor to the west of the subject site.

Page 16

                                          [16]




Photographic Plate 5 – view of the maintained powerline easement between Cooroy Noosa
Road and Tewantin National Park. The Carramar Care facility is to the left of the roadway
out of frame




Photographic Plate 6 – view of Tewantin National Park, to the south of the site, showing
evidence of recent controlled burn.

Page 17

                                       [17]




Photographic Plate 7 – view of eastern portion of Lomandra Place Bushland Reserve
showing the invasion of Sphagneticola trilobata over width of waterway.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.