Engineering Report
Noosa on Weyba
3.3 Existing Road Upgrades
The development proposes upgrades to a number of existing roads. Upgrades to Hollett Road and Tidswell
Road are proposed to provide access points to the development. These roads are currently unsealed and
will require full road reconstruction.
It is proposed that the upgrade of existing Council roads will be undertaken on behalf of Councilor by
Council, at an agreed cost to the development. As these roads will be also be adjoining environmental
sensitive areas, a combination of low speed signage, traffic calming devices and intentional road geometry is
proposed.
Upgrade works are proposed in accordance with Table 3-1 below.
Table 3-1 Scope of Existing Road Upgrades
Section of Road Current Road Current Carriageway Proposed Width I Type
Reserve Width (m) Formation
(refer SK101)
Collector Type 2,
Hollett Road (East) 30 Unsealed
7.4m pavement
Rural Road
Hollett Road (West) 30 Unsealed
9.0m pavement
Rural Road
Tidswell Road 30 Unsealed
9.0m pavement
3.4 Concrete Works
3.4.1 Shared Footpath
For all trunk collector roads a 2.5m wide shared concrete footpath has been assumed to one-side. A shared
footpath connection is also proposed between the eastern and western section of Hollett Road. This link has
been provided to ensure direct pedestrian and cycle connectivity to both sides of Walter Hay Drive. A further
western link extension is also proposed along Hollett Road (west)with connection to Eumundi-Noosa Road.
Cardno Sketch SK100 indicates the proposed shared footpath locations.
Generally, it is proposed to located the shared footpath on the standard alignment, however it is noted that
some cases the footpath may be further offset to accommodate existing significant vegetation. The final
alignment will be determined during detailed design and subsequent development applications.
3.4.2 Kerb
It is proposed to utilise a combination of edge restraint, barrier and mountable type kerbs, depending on
required road profile. Protection of park and open space areas will be achieved by either barrier kerb or
bollards, or a combination of both.
Management and control of stormwater runoff will also determine the type of kerb to be adopted on each
section of road.
November 2012 Cardno 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 5 of 37 Appendix 3 - Civil Engineer Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 37.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.