Engineering Report
Noosa on Weyba
5 Sewerage Reticulation
A sewerage network analysis has been undertaken to determine the impact of the development on the
external sewerage infrastructure and develop a servicing strategy for the site.
Discussions with Unitywater have indicated that planning for the region was out-dated and therefore not
available. Unitywater has indicated that the existing network is generally adequate, with little operating
issues. In order to undertake the network analysis, GIS and existing pump station design data was provided
by Unitywater.
The proposed development is located within the Noosa Coastal sewerage scheme. This scheme consists of
multiple local catchments that discharge to the Noosa Heads Sewage Treatment Plant (STP). The
Noosaville Industrial catchment is a small local sewerage catchment containing three small pump stations,
discharging to a larger pump station (NVL011)located to the north of the development. It is proposed that
the development would discharge to the Noosaville Industrial catchment.
For further details refer to the Water Supply and Sewerage Analysis prepared by Cardno dated 22nd October
2012.
5.1 External Connections
Connection to the external network is proposed at the existing pump station NVL011 within the Noosaville
Industrial catchment. Connection would be discharged via 400 metres of 150 mm diameter rising main along
Walter Hay Drive.
A secondary connection point is also proposed to service Precincts J, K and L at the existing 150 mm
diameter main along Lake Entrance Boulevard.
Cardno Sketch SK600 indicates proposed connection points to the existing network.
5.2 External Augmentations
Networks analysis has determined the impact of the development on the existing sewer network from the
proposed connection point to the Noosa STP. The network analysis has included existing catchment
demands and growth projections. The following infrastructure has been assessed:
> Pump Station NVL011 -
Current spare capacity of 20% of the development yield requires augmentation
to accommodate full development yield;
> Eenie Creek Road Trunk Mains -
Analysis indicates that trunk mains do not surcharge with inclusion of
full development yield;
> Pump Station NVL040 Analysis indicates that pump station can accommodate additional development
-
yield, however operating at a lower efficiency; and
> Noosa STP -
Analysis indicates the Noosa STP requires augmentation to accept the full development
yield. Unitywater has advised that the augmentation of the Noosa STP is proposed, with a completion
date scheduled for December 2015. It is expected that following the STP augmentations, the STP will be
sufficient to accommodate the development loads.
5.3 Internal Network
An internal sewerage network been developed utilising a conventional sewer system consisting of a network
of mains ranging in size from 150 mm to 225 mm. Analysis has indicated that the use of gravity mains at
minimum grade will be able to service the development.
Due to the topography of the site, several pump stations are required to convey flow to the external
connection points. Three small pump stations are required to service the Precincts B, D and E on the south
eastern corner of the development. A larger pump station is required to convey flow to the external
catchment.
November 2012 Cardno 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 5 of 37 Appendix 3 - Civil Engineer Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 37.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.