Change to Existing Approval - OPW11/0116.01

of 52

Text shows just the words. Original shows the document exactly as it was published.

Very large file (40.8 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

    2.   INTENT OF CONCEPT CONSTRUCTION MANAGEMENT PLAN


This Concept Construction Management Plan is intended to provide an indication of how works may be undertaken by the
contractor, likely environmental impacts and intended control measures.

The contractor is to prepare a final construction management plan prior to commencing works. The contractors
methodology, plant, equipment, scheduling etc may vary from that indicated here. Any changes to the intended methodology
that may increase the impact of the works is not to be implemented without further discussion with DERM.


    3.   DESCRIPTION AND PURPOSE OF WORKS


With the exception of those areas already protected by rock works, Noosa River Spit is currently experiencing erosion along
its full length, including the southern end of the Noosa River Spit. While this is reducing amenity along what was once a
popular recreational beach, there is also the potential for continued erosion to breach the Noosa River Spit, which could have
very serious impacts.

A number of options were considered [ICM 2010 report). The preferred option includes [Figure 3):
     .
          Submerged curved "closure" [sand-filled geotextile mega-containers) designed to create an enclosed, stable
          beach and lagoon area
     .
          Dredging for interim navigation and associated foreshore nourishment
     .
          Training wall [sand-filled geotextile mega-containers) to provide a control point for the southem channel
     .    Wall [sand-filled geotextile mega-containers) to prevent erosion along southern end of the Noosa River Spit
     .    Two groynes [2.5m3sand-filled geotextile containers) to stabilize the upstream beach




Figure 3: Proposed Strategy




                                                                                                                             2

Used in these records

About this file

File size
40.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Change to Existing Approval - OPW11_0116.01.pdf · 40.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.