33. A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
be imposed on construction works during the maintenance period, which is a minimum period
of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
Developer for the works.
34. The works to become Council assets will not be accepted "On Maintenance" until the
landscaping is completed.
35. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations from Council's standards exist, then Council standards shall apply
5 REFERRAL AGENCY CONDITIONS
Not Applicable.
6 APPROVED PLANS
The approved plans for this development approval are listed in the following table:
Plan No. Rev. Plan Name Date
ED 7006 OPW-01D Operational Works Landscape Plan by Element 30 May 2007
Design
F06-012 2 of 21 G Site Plan by F3 Design and Architecture 6 July 2007
F06-012 3 of 21 G Floor/Surface Levels by F3 Design and Architecture 6 July 2007
F06-012 4 of 21 G Ground Floor Plan by F3 Design and Architecture 6 July 2007
F06-012 2 of 21 E Site Plan Erosion & Sediment Control by F3 Design 28 May 2007
and Architecture
0127 – R01 A Stormwater Drainage Strategy by Contour 8 June 2006
Consulting Engineers
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged
with this application along with the appropriate fees.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
Page 5 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
ECM_10452652_v1_Decision Letter - Change to an Existing Approval - 010 2007 00000743 002 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 61 KB (small file)
- File type
No other editions are linked here.