ORDINARY MEETING MINUTES 15 NOVEMBER 2018
a. traffic management during all aspects of the construction phase
including:
i. a Traffic Management Control Plan in accordance with the
Manual of Uniform Traffic Control Devices (MUTCD) detailing
all temporary signage and traffic control measures prior to
construction
ii. maintenance of safe pedestrian access for the areas affected
by the works during and after daily construction has ceased
iii. proposed fencing to the site during the construction phase of
the development
iv. approval of the Traffic Management Control Plan by the
Department of Transport and Main Roads (DTMR) for any
works on State controlled roads
v. provision for worker car parking
b. maintenance and protection of water quality and existing drainage
lines through the construction site, through the implementation of
appropriate erosion and sediment control measures
c. works programme identifying key components of the works and their
respective durations
d. establishment of a communication protocol with the general public,
adjoining owners, emergency services and local businesses to
advise of agreed construction times, impacts on traffic, services and
other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
f. details on the location of external fill/dump sites, the haulage route,
type of vehicle to be utilised during filling operations and frequency
of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense
g. it is acknowledged that the preliminary Construction Management
Plan will be a draft document requiring finalisation upon appointment
of the Principal Contractor employed to construct the works and a
final document will be required to be submitted at the Pre-Start
Meeting for the project.
Damage to Services and Assets
62. Any damage caused to existing services and assets as a result of the
development works must be repaired at no cost to the asset owner at the
following times:
a. where the damage would cause a hazard to pedestrian or vehicle
safety, immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing
services and assets must first be referred to the relevant service authority
for approval.
B. Note the report is provided in accordance with Section 63(5) of the Planning Act
2016.
Page 30 of 43
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.