Council archive · source document
Town Planning Report - Other Change Composting Facility · 132005.638.06
“Specialist services and practical solutions”
documents under part 5 Development Approval - 132005.638.04). The approved BFMP
requires provision of a fire trail to the north of the existing Cleanaway Depot.
Having regard to the Bushfire Overlay Code, the following comments are provided:
o The development maintains the safety of people and property from the adverse impacts
of bushfire (PO1).
o The proposed mitigation measures under the BFMP will have no further impact on the
biodiversity values to the north, with an existing bushfire trail to be maintained (PO2).
o While the development is not connected to a reticulated water supply, suitable firefighting
equipment and appropriately sized water tanks will be designed by the hydraulic
consultant to meet current firefighting standards for the development, given the unusual
nature of the site (PO3).
o The development forms part of the essential community infrastructure and does not
increase the level of risk from bushfire (PO4).
o The proposed development will not adversely affect the impacts of bushfire on hazardous
materials manufacturing or storing in bulk quantities (PO5).
o There are no residents associated with the development and appropriate evacuation of the
site can be provided for staff and patrons attending the site as an ongoing operational
requirement under the BFMP (PO6); and
o Adequate fire breaks and access for firefighting and other emergency vehicles are currently
provided in accordance with the BFMP (PO8).
The proposed development complies with the Bushfire Hazard Overlay Code.
10.2.4 Flood Hazard Overlay
Under the Flood Hazard Overlay, the site is subject to flooding during a 1% AEP event (refer
Figure 10).
Figure 10 – Extract of Flood Hazard Overlay Map (Source: Interactive Mapping)
23026 – Noosa Resource Recovery Centre (NRRC) – Composting Facility Page 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Town Planning Report - Other Change Composting Facility .pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.