Noosa Iconic Panel.                                      Decision Notice — Approval with conditions          ,
                  Material change of use (Visitor Accommodation Type 4 - Conventional, Entertainment &
                 Dining Business Type 1 — Food & Beverages, .& Retail Business Type 2 —- Shop & Salon)
                                                       9, 11, 13 & 19 Hastings Street, Noosa Heads
                                                                                    21 May 2009

83.   The use of vibratory equipment of any kind is not permitted to be used (including
      vibrating rollers and the use of vibrating installation techniques for sheet piling and
      other construction vibrations caused by excavating, earthmoving or demolition
      machinery or other similar construction techniques) unless approved and supervised by
      a Certified Geotechnical Engineer. Under such circumstances the operator of such
      equipment shall at all times comply with the directions of the Geotechnical engineer.
Site Stability           ,
84.   A Geotechnical Engineer or similar qualified expert shall assess the soil condition on
      site, determine the soil classification, establish whether any measures are required to           °
      protect the stability of adjoining buildings and/or structures and/or services and/or
      lands, and make recommendations on the type of foundation system(s) best suited for
      the proposed development. The recommendations of this report shall be incorporated
      into the design and construction of the proposed development.
85.   Should the recommendations of the geotechnical report require any part of the works
      (including excavation, retaining structures, tie backs etc) to be temporarily or
      permanently constructed within any adjoining property a letter of authority from the
      adjoining property must be obtained.
86.   The excavation of the site and the construction of the proposed works must not have
      any adverse affects on the stability of adjoining buildings and/or structures and/or
       services and/or lands. In this regard a Registered Professional Engineer Queensland                    ,
      must supervise the excavation of the site and the construction of the new works to
      determine whether any additional measures are required to protect the stability of
       adjoining buildings and/or structures and/or services and/or lands.
Acid Sulfate Soils
87.    Areport on the Identification and Mitigation of Acid Sulfate Soils, prepared in                        ‘
       accordance with Part 6 of SPP2/02 Guideline: Planning and Managing Development                         “
       Involving Acid Sulfate Soils is to be submitted for approval by Council’s Chief                        "
       Executive Officer 5 working days prior to the commencement of any new building                         |
      works.                                           ,                                                      :
Construction & Demolition Issues
 88.   A Condition Survey must be carried out on adjoining buildings, structures and services
       prior to any demolition, excavation or construction works taking place on site. If
       distress already exists, a photographic survey should be undertaken, the distress
       measured and a plan to monitor changes to distress shall be implemented.
 89.   A Demolition & Construction Management Plan for the development shall be                               |
       submitted to and approved by Council at least 5 working days prior to the                              ,
       commencement of any Demolition or Building works or at least 5 working days prior                     =
       to the pre-start meeting for Operational Works. The Demolition & Construction
       Management Plan shall include but not be limited to:                                                   4
       89.1   Site working hours;                                                                             .
       89.2   Communication and consultation processes with surrounding premises and
              Hastings Street stakeholders;
       89.3   Control and suppression of:         ,                                                           |
              89.3.1 Noise

 Page 12 of 20

Used in these records

About this file

File size
8.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

001A9301.001.pdf · 8.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.