8. All vegetation shall be protected from interference resulting from clearing or construction
activities by:
8.1. Clearly marking the 2 Banksias to be retained with flagging tape;
8.2. Installing protective fencing around the drip line of the trees;
8.3. Stockpiling, storage and vehicle parking occurs in already cleared areas and does not
cause interference with trees; and
8.4. Low impact construction techniques are used around trees to minimise interference
with the trees.
9. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:
9.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
minimum of 10 metres between edges of heaps.
9.2. Disposal for firewood.
9.3. Disposal for landscaping purposes.
10. The applicant is advised that burning off is an unacceptable method of disposal.
11. Screening vegetation consisting of native, endemic species shall be planted to all setback
areas and planted in accordance with Council’s Landscaping Plants and Guidelines PSP 3.
In this regard the northern boundary setback area near the lower level bedroom 3 shall be
planted at a higher density.
General – Planning Assessment
12. The development shall be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood due to the creation of excessive noise, lighting
nuisance, or other emissions.
13. Buildings and structures (including swimming pools, sheds, tennis courts, or outbuildings)
shall not be constructed under overhead electricity transmission lines, or within any
easements.
14. All hot water systems installed shall be either solar; electric heat pump; or gas (LPG or
natural).
Operational Works Assessment Branch Earthworks
15. Earthworks required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any natural
watercourses.
16. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification.
Roof Water & Stormwater Drainage
17. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
that is installed to ensure water from the rainwater storage system or tank is used for external
uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
swimming pools, outdoor cleaning, etc) and for internal (ground floor) use in washing
machine cold taps and toilet cisterns. All rainwater tanks are to be designed and installed in
accordance with the Queensland Development Code (QDC) current at the time of building
approval, and shall be part of the plumbing application for approval. The location and capacity
of the tanks shall be clearly shown on the plans submitted for Building Works approval and
any overflow shall be directed to the common property stormwater drainage system.
Page 3 of 7
Document Set ID: 23789626
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - 132010.574.01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 159 KB (small file)
- File type
No other editions are linked here.