Minor Change Existing Approval - 132010.574.01 (As Published)
Geotechnical
18. A geotechnical report, prepared by a registered professional engineer shall be obtained, and
it should either:
18.1. certify that the site is not at risk from landslide emanating from the site or from other
land; or
18.2. identify methods of stabilising all buildings, accessways and uses areas; and where
the geotechnical report identifies methods of stabilising buildings, accessways and
uses areas. The development shall implement those methods, which are
recommended.
Sediment and Erosion Control
19. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard, a plan detailing the methods of controlling erosion and sediment in accordance
with the Healthy Waterways document and fact sheet series titled “Controlling Stormwater
Pollution on your Building Site dated 2006” are required to be submitted with the application
for a Building Works Permit.
General – Operational Works Assessment Branch
20. Any damage caused to any public utility during the course of construction shall be repaired
to Council’s standards and at no cost to Council.
21. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
22. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Contributions
23. The applicant must pay contributions towards trunk infrastructure in accordance with the
following Planning Scheme Policies and Council Policies:
(a) Planning Scheme Policy 12 – Public Open Space Contributions;
(b) Planning Scheme Policy 13 – Contributions in Lieu of Off Street Parking;
(c) Planning Scheme Policy 16 – Sewerage Headworks Contributions;
(d) Planning Scheme Policy 17 – Water Supply Headworks Contributions;
(e) Planning Scheme Policy 20 – Pathway Trunk Network Contributions;
(f) Council Policy – Rural Roadworks Contributions;
(g) Council Policy – Master Drainage Contributions.
For material change of use of premises approvals the contributions must be paid prior to the
commencement of use, for reconfiguring a lot approval contributions must be paid prior to
Council approval of the plan of subdivision.
The actual amount of the contribution must be calculated and paid in accordance with the
Planning Scheme Policies and variations due to indexation current at the time of payment.
5. REFERRAL AGENCIES
Not applicable.
Page 4 of 7
Document Set ID: 23789626
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - 132010.574.01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 159 KB (small file)
- File type
No other editions are linked here.