5. Excavation of the basement to the underside of capping beam level.
6. Bracing installed to support the structure during construction.
7. Excavation to be continued in approximately 2-3m increments to allow steel and shotcrete
to be installed.
8. Repeat methodology until underside of bottom basement slab RL is reached.
NOTE:
This methodology does not incorporate any anchors within the site or encroaching into neighboring
properties. It will not have any adverse effect on adjoining infrastructure, buildings or vegetation.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.