NOOSA COUNCIL IDAS Development Application Decision Notice                                                    4 of 9


Vegetation Protection & Weed Removal

12.    Existing trees on site and within the road reserve are to be retained, except where required to be removed
       due to a building approval or the conduct of an approved use. Driveways and buildings sites should be
       designed to avoid the removal of native vegetation.

13.    The applicant shall reinstate and landscape the acoustic buffer mound along the north and the east
       boundaries of the site with dense vegetation generally in accordance with plan No. 9802R/A dated 5 April
       1998 by Callaghan & Toth Consulting Engineers and which was part of Approval 12611DA (Date of
       Decision 28/09/1998). All parts of the mound shall be constructed within the boundaries of the lots. A
       Development Permit for Operational Works for earthworks and the landscaping of the mound is required.

14.    The landscaped acoustic buffer mound is to be protected by Covenant. The Covenant area shall cover
       the whole sound attenuation / visual buffer area.

15.    Footpath improvements such as topsoiling, grassing, and tree planting are required to the Armitage Court
       frontages of the site (including the south boundary line of Lot 2) in accordance with Planning Scheme
       Policy PSP03 Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.

16.    All Class 1, Class 2 and Class 3 pest plants declared under the Land Protection (Pest and Stock Route
       Management) Act 2002 and including all Camphor Laurel trees on the property are to be controlled on the
       site prior to Council endorsement of the Plan of Survey. In this context “controlled” shall mean, for class 1
       and 2 pests, completely eradicated. For class 3 pests it shall mean removal of the plants where they
       threaten environmentally significant areas of the site such as riparian zones and areas of natural
       vegetation.
       Where class 3 plants are removed as a result of this condition and there is not sufficient natural
       regeneration of native species, the areas shall be replanted with endemic native species so that a
       sustainable natural ecosystem is restored.
       Council’s Conservation Management Supervisor will not inspect the site until 30 days after the weed
       treatment and replanting is complete.
17.    If there is any cleared vegetation it shall be suitably processed by one of the following methods and
       removed from the site:-

       17.1. Processing through a wood chipper or shredder. The resulting mulch is to be stockpiled loose in
             heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum of 10 metres
             between edges of heaps.

       17.2. Disposal for firewood.

       17.3. Disposal for landscaping purposes.

       17.4. Transport to alternative site for breaking down materials provided that all necessary permits have
             been obtained to allow the alternate site to be used for this purpose.
       The disposal method for clearing works is to be submitted in conjunction with an application for a
       Development Permit for Operational Work. The Applicant is advised that other methods may be
       considered provided full details of the method are submitted.

       The Applicant is also advised that burning off is an unacceptable method of disposal.
Roof Water & Stormwater Drainage

18.    Any works associated with this development shall not adversely affect the existing drainage conditions on
       the adjoining properties by diverting and/or discharging additional stormwater runoff, blocking the natural
       overland runoff from these properties or cause additional stormwater ponding.

19.    The roof and paved area runoffs from Lot 1 shall be collected and discharged into Council’s drainage
       system without adversely impacting on Lot 2 or any adjoining property. Should any inter-allotment
       drainage from Lot 1 encroach onto Lot 2, creation of a private drainage easement 1.5m wide shall be
       required.

20.    All site stormwater drainage shall be by means of a gravity system.




NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@380d2440\@[email protected]

Used in these records

About this file

File size
40 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00001255.001 [As Published].pdf · 40 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.