Water Quality and Drainage Code
Noosa Council Plan July 2020
Performance and Acceptable Outcomes Table
Version: 2020
Performance Outcomes Acceptable Outcomes Solution1 Comments Council Use
allowance for climate change impacts
(including rainfall intensity and sea level
rise), in accordance with PSP6 Engineering
Design Standards – Roads, Drainage and
Earthworks.
PO3 AO3.1
Stormwater drainage infrastructure conveys run- Stormwater drainage infrastructure meets the
off in a manner that allows roads to deliver desired standards of service for roads
N/A
desired standards of service appropriate to the functionality set out in PSP6 Engineering
local conditions and local stormwater drainage Design Standards - Roads, Drainage and
characteristics. Earthworks.
PO4 AO4.1 RO4.1
Stormwater infrastructure is compatible with The location, design and construction of Refer to RO2.1.
existing infrastructure, allows for easy access for stormwater drainage structures is in
the ongoing maintenance by Council, is cost accordance with PSP6 Engineering Design
effective across its design life. Standards - Roads, drainage and
earthworks.
AO4.2
Where infrastructure is located on private
land an easement is dedicated over the
N/A
infrastructure in accordance with PSP6
Engineering Design Standards - Roads,
drainage and earthworks.
AO4.3 RO4.3
Any alterations or repairs to infrastructure as The proposal complies.
a result of the development are made at no
cost to Council.
AO4.4 RO4.4
Development avoids stormwater inflow and The proposal complies. Stormwater will
infiltration to the sewer infrastructure be design to avoid inflow and infiltration
network. into the sewer infrastructure network.
AO4.5 RO4.5
Stormwater infrastructure is designed to The proposal complies.
minimise maintenance costs and the
requirement for specialized equipment for
1
Solution: Acceptable Solution Page 2 of 10
A/S Alternative Solution D:\JOBS\20-Jobs\20169 - 101 & 105 Eumundi Noosa Road, Noosaville\Civil\Reports\SBSMP\Working\Appendices\20169 - NSC Water Quality and Drainage Code 2020.docx
N/A Not applicable to this proposal Job: 20169
Rev: 0
Site Address: 101-105 Eumundi Noosa Road, Noosaville 30/11/2020
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.