RECOR Preliminary Stormwater Management Report - 20220198
SITE DETAILS
2.1. Existing Site Description & Drainage
The existing site, known in real property terms as Lot 148 RP160425, is located at 3 Delorme Street. The existing site
contains a residential dwelling with a total site area of 832m².
2.2. Existing Drainage Patterns
The subject land is located in moderately sloping terrain with the land generally falling from the west to east at
typically 10 to 15%. The run-off from the existing developed site typically drains as overland surface flows to the
eastern portion of the site, however sandy soils are typical of the locality and a significant portion of surface run-off
is expected to infiltrate into the site soils.
Roof run-off is conveyed by downpipes below ground with an outlet within the Delorme Street frontage kerb
observed as the discharge point for these pipes. A downstream pit at the end of Delorme St will ultimately collect
the roof drainage from the kerb and gutter system.
Figure 2.1 - Site Locality Plan (Noosa Council Intramaps, 2022)
Project number 20220198
File RECOR Preliminary Stormwater Management Report - 20220198, 2022-08-19 Page 5 of 15
Revision 1
P +61 7 5211 1003 A 75 Noosa Dr, Noosa Heads Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.