Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

RECOR Preliminary Stormwater Management Report - 20220198

of 28

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

 STORMWATER QUANTITY

     3.1. Pre-Post Comparison
As the development proposes to increase the impervious area of the site by approximately 396.6m² (from 267m² to
664m²), there is likely to be an increase in peak flows from the site. The site has therefore been modelled using the
DRAINS software to assess the impact on peak flows, comparing the existing site conditions to the proposed
development.

In accordance with ARR2019, an Initial Loss-Continuing Loss (IL-CL) model has been used to assess the site against
the ensemble of storm temporal patterns for the East Coast North region. The loss parameters and temporal patterns
have been imported from the ARR Datahub, and rainfall intensities have been imported from the Bureau of
Meteorology IFD rainfall data allowing for a 20% increase to rainfall depths to account for future climate change
patterns.

The parameters obtained from the Australian Rainfall and Runoff (ARR) Data Hub for the location and the rainfall
IFD data obtained from the Bureau of Meteorology have been imported into Drains to generate the storm events.
The models have been run using the ensemble of storm events for 1EY, 50%, 0.2EY, 10%, 5%, 2% and 1% Annual
Exceedance Probability (AEP) for durations from 1 minutes to 24 hours to determine the critical storm duration and
the mean peak flowrate from the storms. Refer to Appendix B DRAINS Modelling Parameters and Results for details
of the parameters used and summary of the results from the modelling.

The model used to represent the development is shown below in Figure 3.1 – DRAINS model layout.




                                                     Figure 3.1 – DRAINS model layout

The configuration of the catchment areas for pre-development, post-development and split post development for
roof water to an attenuation tank are shown in Figure 3.2 – DRAINS Pre-development catchment, Figure 3.3 – DRAINS
Post-development catchments and Figure 3.4 – DRAINS Split Post-development catchment respectively.




Project number 20220198
File RECOR Preliminary Stormwater Management Report - 20220198, 2022-08-19                                    Page 7 of 15
Revision 1


P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com
Log in to download the original file

RECOR Preliminary Stormwater Management Report - 20220198.pdf · 4.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.