25.    Sediment and erosion control measures must be in place prior to works commencing. If such measures
       are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
       sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
       natural waterways. Although the sediment and erosion control measures have been approved on drawing
       No. 16017-OW1A, Council’s Manager – Land Development may request further controls to be installed
       should approved measures be inefficient.

26.    Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement of
       satisfactory “As Constructed” records shall be submitted to Council.

       As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer (RPEQ) for
       design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all
       services and structures. All of which shall be submitted to Council for checking and for Council’s records.
       The data must fully detail levels for all engineering works including but not limited to drainage structures,
       finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
       As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
       www.adac.com.au) and Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
       Drainage and Earthworks.

       Approval of works shall not be granted until all As Constructed information has been
       supplied and accepted by Council.

27.    A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
       on construction works during the maintenance period, which is a minimum period of 12 months duration.
       Such bond must be lodged by, and shall only be accepted from the Developer for the works.

28.    The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
       completed.

29.    These works are also to be in compliance with the relevant conditions of Development Permit No.
       2006/1748.

30.    Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
       from the day this permit takes effect during which time all conditions must have been complied with and
       the Plan of Survey lodged with the Council for endorsement.

31.    Notwithstanding that Council has checked the plans with due care, where it is found during construction
       that variations from Council's standards exist, then Council standards shall apply
Water & Sewerage
32.    The approved sewerage plans are:
        16017-OW1 – Operational Works and Drainage – sewer detail only
        16017-OW2 Nov 2006 – Access Tunnel Plan

33.    All work to be carried out to the standards and requirements of Noosa Council in accordance with
       Planning Scheme No. 6 – Engineering Design Standards - Water Supply & Sewerage.

34.    A copy of the job specification is to be provided to Council’s Inspector within seven (7) days of the date of
       this Decision Notice, and prior to commencement of works.

35.    The names of any proposed contractors for works are to be submitted in writing, together with copies of
       current Public Liability and Workers Compensation Insurances together with certificates of currency for
       those policies, for consideration by the Assessment Manager seven (7) days prior to pre-start meetings
       and commencement of works.

       A separate letter will then be issued approving the contractor (or otherwise) for the works. No other
       contractor or subcontractor shall be engaged to carry out the works or any part of the works without the
       written approval of the Assessment Manager.




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@9801a144\@[email protected]

Used in these records

About this file

File size
40 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00001670.001 [As Published].pdf · 40 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.