Attachment 7- Site Based Stormwater Management Plan
Attached to the e-mail Response to Information Request - RAL18/0023.
Plans and drawings: the text below has words only, no drawings.
Stockpiles Stockpile locations should be identified before the commencement of works. Ideally, they should be located in a flat area at least 15m from any water body or stormwater inlet. Sediment fences should be installed downslope of all erodible stockpiles, and upslope protection measures should be used (i.e. sandbags or sediment fence) to divert runoff in the event of rain. At the end of each working day stockpiles should be covered with geofabric if rain or high winds are forecast. Street Sweeping Ensure that local roads are swept as required. This will minimise the potential for sediment tracked onto the road to be washed into the stormwater system. If a large quantity of sediment is being tracked onto the surrounding streets the stabilised entry/exit point may need to be raked or reinforced with rock to provide more effective sediment removal for vehicles. Erosion Control Matting and Permanent Stabilisation Exposed areas onsite should be permanently stabilised (i.e. with turf) as the construction works progress. Erosion control matting or mulching should be used as a temporary measure to stabilize exposed areas before permanent stabilisation can be undertaken. Monitoring Monitoring and recording of the performance of the drainage control devices including are to be undertaken in accordance with local government requirements. It is further recommended that the proposed construction works are undertaken during periods of dry weather to reduce the potential for sediment to be transported off site during construction. 4.2 OPERATIONAL PHASE The internal drainage system has been designed to include SQIDs in the water quality treatment train for the proposed development. Refer to the conceptual drainage plans in Appendix A for details. 4.2.1 Bioretention Basin Bioretention basins are densely vegetated filtration devices, where runoff (for small/frequent storm events) enters the basin and is filtered through a filter media layer (e.g. sandy loam) as it percolates downwards. Bioretention basins often have an extended detention volume above the filter media which increases the volume of runoff treated through the system. The runoff is treated as it passes through the system through fine filtration, absorption, and Site Based Stormwater Management Plan Page 7 of 20 1856-SBSMP-01_Version 2.0 (April 2019)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.