Traffic Impact Statement
Detail of building configuration - pit sealing
The layer composition is to be considered as a suggestion. Equivalent sealing systems are equally possible, but must be matched to
the customer’s application. Lay all components according to the manufacturer’s working instructions.
Typical structure for pit sealing
1 2 5 4 6 3
Sealing specifications
No. Layer Recommended implementation Scope of delivery
1 Pit Top platform of the MultiBase U10 / U20 as frame structure. KLAUS Multiparking
Pond liner 300 g/m², laid continuously.
To be performed by the cus-
2 Separating layer Also cover corner connections and screw projections, and fix using a suitable
tomer
adhesive.
3 Water drain PVC foil flange, diameter 50 mm, for gluing (by the customer) to the seal. KLAUS Multiparking
PVC pond liner, thickness 0.5 mm, laid continuously.
To be performed by the cus-
4 Sealing Glue the pond liner and foil flange over the entire surface using a suitable adhe-
tomer
sive.
High performance adhesive tape 50 mm, for circumferential fastening of the To be performed by the cus-
5 Edge fastening
sealing. tomer
To be performed by the cus-
5 Protective layer Pond liner 500 g/m², laid continuously and extending over the border of the pit.
tomer
Product data MultiBase U10 EB 588.52.620-005 04/2023 English 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.