24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                    EWSM- 1 EROSION AND SEDIMENT CONTROL (STORMWATER MANAGEMENT)
                                                                                                                                                          Version 1


Hierarchy of Control (HOC): 1. Eliminate 2. Substitute 3. Isolate 4. Engineer 5. Admin 6. PPE

                                    Sediment controls are not in good       5    All erosion and sediment control measures should be inspected:
                                    order and working effectively                 - At least daily when rain is occurring;
                                                                                  - At least weekly (even if work is not occurring on-site)
                                                                                  - Within 24 hours prior to expected rainfall; and
                                                                                  - Within 18 hours of a rainfall event of sufficient intensity and
                                                                                       duration to cause on-site runoff
Control water movement through      Mass soil loss and        significant   5    Divert clean stormwater (upslope water) runoff outside the site so that   Site Manager
the site                            sediment runoff site                          it does not flow through the site                                         HSE Advisor
                                                                                 Sediment traps must be installed and operated to both collect and
                                                                                  retain sediment.
                                                                                 All erosion and sediment control measures, including drainage
                                                                                  control measures, must be maintained in proper working order at all
                                                                                  times during their operational lives.
Material Stockpiles                 Contaminated topsoil                    5    Topsoil stockpile needs to be separated to other materials and            Site Manager
                                                                                  located at the undisturbed area
                                                                                 Topsoil is stockpiled at maximum 2m height
                                                                                 Long term spoil stockpiles (> 28 days) to be covered or stabilised.
                                    Cross-contaminated with topsoil         5    Sufficient land area must be provided for the short-term stockpiling of   Site Manager
                                                                                  construction materials.
                                                                                 Ensure excavated material is not placed adjacent to protect
                                                                                  vegetation, stream banks, or within locations where it may become
                                                                                  an unacceptable source of sediment runoff.
                                                                                 These stockpiles should ideally be located within areas that would
                                                                                  eventually need to be disturbed anyway.
                                    Excess sediment runoff                       Material stockpiles should be located away from overland flow paths
                                                                                  and concentrated overland flow
                                                                                 Stockpiles of erodible materials (e.g. earth and sand) need to be
                                                                                  located within the site’s sediment control zone.
Stormwater kerb inlets in active    Sediment socks fall into kerb inlet     5    Daily check on sediment controls on council kerb inlets                   Hutchinson Builders
construction areas as well as the                                                                                                                           Foreman/ HSE Advisor
basement level receiving
deliveries areas are to be          Sediment deposition within creeks       5    Ensure all the sediment controls are installed as approved Erosion        Hutchinson Builders
protected                           and wetlands can cause long-term              and Sediment Control plan and in good order                               Foreman
                                    changes to aquatic ecosystems
                                    and plant species (e.g. through
                                    weed infestation).                                                                                                      Workers



                                                                                                                                                                                   2
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.