24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Environmental Management Plan
24647 – 71 SEAVIEW TCE SUNSHINE BEACH

Further to documenting a hazard or event, the type and extent of investigation will be determined by the Team HSE Manager.
Management will review all information available and consider the risks associated with the hazard or incident. All events resulting in
injury, disease or other harm will be investigated to determine the cause of the event. The result of the investigation will be reported
to the Management Team. Where a systematic breach has been identified a corrective action will be raised in accordance with
Environmental Management Systems Manual section 7.8.2


7.5             Incident and corrective action reporting to the Principal
The Principal shall be consulted on what environmental occurrences are considered to be incidents, prior to any works commencing.
The Principal shall be notified of the occurrence of an environmental incident, or where there is any uncertainty about any incident.


7.6             Reporting incidents to regulatory authorities
The state regulatory body shall be notified in writing of any incident which has caused, or may cause serious or material environmental
harm. The Project Manager is responsible for ensuring incidents are reported to regulatory authorities within the required time frames.
A written notice detailing the following information must be provided to the state regulatory body within 14 days only when the released
contaminates exceed the allowable limit. The following are details that are required to be included on the notification:

    The name of the operator, including their registration certificate number

    The name and telephone number of a designated contact person
    Quantity and substance released

    Person(s) involved

    The location and time of the release

    The suspected cause of the release

    A description of the effects of the release

    The results of any monitoring performed in relation to the release

    Actions taken to mitigate any environmental harm caused by the release

    Proposed actions to prevent a recurrence of the release.


7.7             Complaints and complaints response
A Community Complaints and Consultation Register HB-HSEQ-F-041 will be established for the project for the purpose of
documenting impacts or complaints from neighbours or community. Incidents involving members of the community or complaints
directly received may require an Incident / Injury / Hazard Report Form HB-HSEQ-F-027-B to be completed and retained on site for
the duration of the project.
Sub-contractors will ensure that any complaints received by them during works are forwarded to site management immediately. Sub-
contractors are not to initiate consultation or communication with community or stakeholders without site management approval.
Complaints shall be managed by the Project Manager, Site Manager or their delegate, in consultation with other relevant stakeholders
so that a timely resolution is achieved. The resolution process shall involve a review of the effectiveness of control measures, which
shall be modified where found to be deficient, and extended to other work areas or practices to avoid recurrence of the issue (refer
Section 9)


8.              Record Keeping & Document Control (EMSM Section 6.3.4)
The following records shall be accessible at the main site office:
    Current and superseded versions of the site specific EMP (all versions)

    Regulatory licences and permits
    Pre-clearance survey (where applicable)

    Regulatory authority inspection reports



HUTCHINSON BUILDERS                                                                                                                  15
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.