24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Environmental Management Plan
24647 – 71 SEAVIEW TCE SUNSHINE BEACH


6.3             Toolbox Training (EMSM 6.3.3)
Ongoing toolbox training using form Toolbox Talk OHSE HB-HSEQ-F-055 shall be prepared and delivered by the HSE Advisor to
ensure that relevant information is communicated to the workforce on an ongoing basis and that feedback can be provided on issues
of interest or concern. For additional information relating to the use and implementation of Toolbox Talk refer to OHSMS procedure
PP:06 Communication on Site.



7.              Communication & Reporting (EMSM Section 6.3.3)

7.1             Internal communications and reporting pathways
The organisational structure described in Section 2 represents the general communication and reporting pathways for the contract.
Signage shall be erected displaying contact details for the Site Manager and persons responsible for responding to incidents and
emergencies.
Hutchinson Builders will ensure consultation / cooperation and consultation occurs with duty holders & site personnel through the
following consultative arrangements and in alignment with the EMSM, and internal OHSMS Procedure PP:06 Communication on
Site:

    Weekly HB Site Meeting

    Weekly Subcontractor Meeting

    Weekly HSE Committee Meeting
    Toolbox and Prestart Meetings (refer Section 6.3)


7.2             External stakeholders
Hutchinson Builders are committed to working with other stakeholders to ensure an amicable approach is taken to the sharing of
infrastructure and resources through specific and open lines of communication.
The Project Manager and Site Manager are responsible for consultation with external stakeholders. Sub-contractors are to notify the
Site Manager of any issues or contact with stakeholders and refer all stakeholders to site management for further information. The
Principal’s Representative will be advised of all stakeholder consultation prior to it occurring and invited to attend meetings and/or
discussions.


7.3             Routine reporting
General Progress Reports shall be prepared monthly using form Project Performance HB-HSEQ-F-049 by the Site Manager or
delegate and made available to the Principal. The report will, at a minimum, provide the following information summaries:

    Any EMP revisions
    Weekly HSE Inspection BIG 8 HB-HSEQ-F-048

    Environmental training

    Results of internal audits

    Non-conformances, incidents and/or proposed actions for rectification or improvement of management procedures, and

    The status of any open non-conformances

    Monitoring results, if requested.

    Project specific reporting requirements.


7.4             Internal reporting – hazards, non-conformance and corrective action
The Project Manager will be responsible for ensuring that all incidents are investigated and reported internally in accordance with the
Hutchinson Builders procedure using form Incident Report Form HB-HSEQ-F-027-B.



HUTCHINSON BUILDERS                                                                                                                14
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.