24647 Seaview Tce Enviro Mgmt Plan
Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).
The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Advance Land Staged Construction
Erosion Risk Soil Loss Rate Max days to Stockpiles
Clearing Allowed and Stabilisation of
Rating (t/ha/year) Stabilisation stabilised
(wks work) Earth Batters >6H:1V
Extreme > 1500 2 5 (80%)
Given the nature of the works there will be opportunities to utilise temporary erosion protection measures
during construction. Diversion bunds are to be stabilised with geotextile or soil binder and if temporary
erosion control is required in other areas, erosion control blankets (i.e. geotextile) or soil binder should be
applied to exposed surfaces, taking note of the maximum days to stabilisation and percentage cover to be
provided (as detailed in Table 2).
The temporary access tracks and vehicle manoeuvring areas will be stabilised using road base, thus
reducing the need for temporary erosion control during construction. Runoff from these areas must
however be directed to stable/lined drainage structures.
Once the excavations for the pool are undertaken, sediment control will be the dominant measure in
managing stormwater runoff until final treatments can be applied to the work area.
5.1. Stockpiles
Stockpiles formed and retained on site should be situated away from any drainage paths. Temporary
erosion protection for stockpiles must be provided in accordance with Table 2. Alternatively sediment
fence can be installed around the stockpiles. A diversion bund or other drainage control measures must be
installed around the upslope side of stockpiles.
6. Drainage Control
Drainage control considers three main principles; diverting external flow before it enters site, directing site
runoff to an appropriate sediment control, and ensuring runoff is conveyed in a non-erosive manner.
A key component of managing surface waters through and within the project site is the diversion of ‘clean’
runoff away from disturbed portions of the site. Clean water is defined as water that either enters the
property from an external catchment and has not been further contaminated by sediment within the site,
or water that has originated from the site and is of such quality that it does not need to be treated in order
to achieve the required water quality standard, or would not be further improved if it was to pass through
the sediment trap specified for the sub-catchment (IECA, 2008).
In diverting clean water around the disturbed portions of the site, it will remain separated from the
sediment laden runoff that is required to be treated within nominated sediment controls. It is important
that clean water diversion bunds are constructed prior to new areas being disturbed to reduce the
likelihood of runoff being contaminated.
‘Dirty’ water on the other hand is described as runoff from the construction site, or exposed footprint that
is not expected to meet the water quality objectives. Dirty water must be collected and directed to an
appropriately designed and installed sediment control. After passing through the appropriate sediment
control, the water may then be classified as clean water.
71 Seaview Terrace, Sunshine Beach - Erosion and Sediment Control Plan Page 5
Hutchinson Builders
17SUN-0024/1600102
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.