24647 Seaview Tce Enviro Mgmt Plan
Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).
The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnList of Referenced Legislation & Codes of Practice – Environment
HB-HSEQ-F-005-A Version 5
Issues Applicable Legislation / Guidelines / Standards Regulating Major Requirements Of Legislation
Authority
Contaminated Soil Protection of the Environment Operations Act 1997 NSW EPA Obtain permit from EPA if offsite transportation and/or disposal required.
Obtain permission from landfill operator for disposal.
All occupiers of land including subcontractors must be notified if a site is
included on the contaminated land register or the environmental land
register
Check with client whether contaminated soil has been documented on
site and whether the appropriate permits have been obtained.
Check with Local council for any local codes or policies
The owner of the site should provide necessary notifications to
occupiers if site is contaminated or included on the environmental land
register
Water Management
Water Use Protection of the Environment Operations Act 1997 NSW EPA No releases of substances to surface waters, groundwater or
Water Management Act 2000 NSW stormwater e.g. cement, building waste, rubbish, hydrocarbons, etc.
unless authorised by an EPA Approval
Minimise volumes of clean water used on site.
Ensure water valves/ taps can be turned off by using meters.
Minimise consumption of water for irrigation on site landscape.
Surface Water Discharge Protection of the Environment Operations Act 1997 NSW EPA No releases of substances to surface waters, groundwater or
Best Practice Erosion & Sediment Control 2008 stormwater e.g. cement, building waste, rubbish, hydrocarbons, etc.
unless authorised by an EPA Approval.
No releases of stormwater off-site into a stormwater drain which results
in the build-up of sand, silt or mud; or the deposition of sediments off
site.
Identify potentially sensitive surface water drainage areas and, where
possible move activities away from sensitive areas.
Use measures to minimise potential for surface water discharges.
HUTCHINSON BUILDERS 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.